8101 W HILLROSE ST 91040

Certificate Information: 8101 W HILLROSE ST 91040

Application / Permit
22014-20000-03972
Plan Check / Job No.
B22VN12074
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
30'-8" x 29'-6" ADDITION TO (E) SFD AND 8'-0" x 11'-5" (91 S.F ) TRELLIS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 LUISANGEL VALENZUELA
Corrections Issued 8/10/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 8/12/2022 APPLICANT
Applicant returned to address corrections 8/26/2022 ALFRED RAMIREZ
Plan Check Approved 3/9/2023 MIROOSH KHACHATOORIAN
Issued 3/9/2023 APPLICANT
CofO in Progress 5/29/2024 WILLIAM WREN
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/28/2022 COLIN LOREDO
Sewer availability Cleared 11/28/2022 MEGAN GODINEZ
Low Impact Development Cleared 1/31/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/31/2023 MEGAN GODINEZ
Grading Pre-Inspection Cleared 2/23/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2023 Partial Approval WILLIAM WREN
Sewer 5/8/2023 Approved WILLIAM WREN
Underground Mechanical 5/8/2023 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 8/19/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/6/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval WILLIAM WREN
Green Building Rough 9/6/2023 Not Ready for Inspection WILLIAM WREN
Wood Frame 9/6/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 9/19/2023 Approved WILLIAM WREN
HVAC-Rough 9/19/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/19/2023 Approved WILLIAM WREN
Underground Mechanical 9/19/2023 Not Ready for Inspection WILLIAM WREN
Wood Frame 9/19/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved WILLIAM WREN
HVAC-Rough 9/25/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 9/26/2023 Approved WILLIAM WREN
Green Building Rough 9/26/2023 Approved WILLIAM WREN
HVAC-Rough 9/26/2023 Partial Inspection WILLIAM WREN
Interior/Exterior Lathing 10/5/2023 Partial Approval WILLIAM WREN
Shower Pan 10/5/2023 Approved WILLIAM WREN
Insulation 10/12/2023 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 10/12/2023 Partial Approval WILLIAM WREN
Pre-Inspection 10/16/2023 Partial Inspection WILLIAM WREN
Drywall Nailing 10/24/2023 Approved WILLIAM WREN
Insulation 10/24/2023 Approved WILLIAM WREN
Pre-Inspection 11/15/2023 Partial Inspection MICHEL ABAJAN
Special/Order Compliance 11/22/2023 Corrections Issued WILLIAM WREN
Pre-Inspection 11/28/2023 Partial Inspection WILLIAM WREN
Pre-Inspection 12/11/2023 Partial Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready WILLIAM WREN
Final 2/22/2024 Not Ready for Inspection WILLIAM WREN
Green Building Final 2/22/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 2/22/2024 Approved WILLIAM WREN
Special/Order Compliance 3/14/2024 Corrections Issued DAVID MATSON
Final 5/1/2024 OK to Issue CofO WILLIAM WREN
Green Building Final 5/1/2024 Approved WILLIAM WREN