5463 N PENFIELD AVE 91364

Certificate Information: 5463 N PENFIELD AVE 91364

Application / Permit
22014-20000-03963
Plan Check / Job No.
B22VN12062
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADD 781.5 SF, (1-BEDROOM AND 1-BATHROOM) TO THE EXISTING 1,498 SF, 3-BEDROOM/2-BATHROOM SINGLE FAMILY DWELLING+ INTERIOR REMODEL
Permit Issued
Issued on 12/5/2022
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 ZAW HAN
Corrections Issued 8/15/2022 ZAW HAN
Applicant returned to address corrections 8/25/2022 ZAW HAN
Plan Check Approved 9/28/2022 ZAW HAN
Issued 12/5/2022 APPLICANT
CofO in Progress 12/8/2023 JOHN KIDWELL
Permit Finaled 1/10/2024 JOHN JANSON
CofO Issued 1/10/2024 JOHN JANSON
Permit Finaled 1/10/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/17/2022 COLIN LOREDO
Sewer availability Cleared 8/17/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 8/23/2022 KIRK LINKLATER
GPI Written Notices Cleared 8/25/2022 KIRK LINKLATER
Low Impact Development Cleared 9/8/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/12/2022 COLIN LOREDO
Hydrant and Access approval Cleared 9/23/2022 LAVEON RIDER

Contact Information

Contractor Jermax Construction Inc; Lic. No.: 1054628-B 7849 CANOGA AVE      CANOGA PARK, CA 91304
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2023 No Access for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/2/2023 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 2/2/2023 Approved PETER FOLLING
PLUMBING-Rough 2/28/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 3/3/2023 Partial Approval PETER FOLLING
Deputy Wood Construction 4/20/2023 Approved PETER FOLLING
ELECTRICAL-Rough 4/20/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Approved PETER FOLLING
PLUMBING-Rough 4/20/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 5/9/2023 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 6/15/2023 Approved PETER FOLLING
Green Building Rough 6/15/2023 Approved PETER FOLLING
HVAC-Rough 6/15/2023 Approved PETER FOLLING
Interior/Exterior Lathing 6/15/2023 Partial Approval PETER FOLLING
MERV13>=Rough 6/15/2023 Approved PETER FOLLING
Insulation 6/21/2023 Approved PETER FOLLING
Drywall Nailing 7/5/2023 Approved PETER FOLLING
Shower Pan 7/13/2023 Approved PETER FOLLING
Final 11/16/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 11/16/2023 Approved JOHN KIDWELL
MERV13>=Final 11/16/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 11/16/2023 Approved JOHN KIDWELL
Final 12/1/2023 Not Ready for Inspection JOHN KIDWELL
Final 12/8/2023 OK to Issue CofO JOHN KIDWELL
Special/Order Compliance 12/19/2023 Approved JOHN KIDWELL