10709 N MATHER AVE 91040
Certificate Information: 10709 N MATHER AVE 91040
- Application / Permit
- 22014-20000-03960
- Plan Check / Job No.
- B22VN12060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN New 495 square feet one story addition at rear of the existing one story residence. ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 11/27/2023
- Issuing Office
- Current Status
- CofO Issued on 8/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2022 | KHUONG TRUONG |
| Corrections Issued | 8/9/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/22/2023 | KHUONG TRUONG |
| Issued | 11/27/2023 | APPLICANT |
| CofO in Progress | 8/28/2024 | WILLIAM WREN |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
| CofO Issued | 8/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/21/2023 | RIDWAN HARDY |
| Sewer availability | Cleared | 5/24/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | NIKKI ZULUETA |
| ZI | Cleared | 6/6/2023 | BRENNEN OBETO |
| Grading Pre-Inspection | Cleared | 7/10/2023 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 10/20/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2023 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Inspection | 12/11/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 12/21/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 1/2/2024 | Partial Approval | MATTHEW NELSON |
| Insulation | 1/5/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/8/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/8/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 2/8/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 2/8/2024 | Corrections Issued | WILLIAM WREN |
| Insulation | 2/8/2024 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 2/8/2024 | Approved | WILLIAM WREN |
| Insulation | 2/14/2024 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 2/23/2024 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 2/29/2024 | Approved | WILLIAM WREN |
| Insulation | 2/29/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/5/2024 | Approved | WILLIAM WREN |
| Shower Pan | 3/5/2024 | Approved | WILLIAM WREN |
| Final | 5/29/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 5/29/2024 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 5/29/2024 | Approved | JOHN COLEMAN |
| Final | 7/15/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/15/2024 | Approved | WILLIAM WREN |
| Final | 8/5/2024 | OK to Issue CofO | WILLIAM WREN |