14057 W AZTEC ST 91342

Certificate Information: 14057 W AZTEC ST 91342

Application / Permit
22014-20000-03955
Plan Check / Job No.
B22VN12036
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20' X 27'-6" ADDITION TO AND CONVERT (E) 12' X 17'-6" SHED TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH 12' X 11'-8" ATTACHED PATIO COVER. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/9/2022 OMAR GARNICA
Corrections Issued 8/9/2022 OMAR GARNICA
Building Plans Picked Up 8/12/2022 APPLICANT
Plan Check Approved 12/20/2022 ANGELICA MARTINEZ
Issued 12/29/2022 APPLICANT
CofO in Progress 5/20/2024 KEVIN BERBERYAN
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/24/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 11/2/2022 ROMAN GUTIERREZ
Sewer availability Cleared 11/2/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 12/15/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 12/20/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2023 Partial Inspection ARAM AVEDISIAN
Special/Order Compliance 5/5/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/15/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/15/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 6/16/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 8/11/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 8/11/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Corrections Issued DAVID ANDERSON
Gas Test 8/11/2023 Approved DAVID ANDERSON
Green Building Rough 8/11/2023 Approved DAVID ANDERSON
HVAC-Rough 8/11/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 8/11/2023 Corrections Issued DAVID ANDERSON
Sewer 8/11/2023 Approved DAVID ANDERSON
Underground Mechanical 8/11/2023 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 8/25/2023 Partial Inspection ROBERT GOLD
BUILDING-Rough-Frame 9/6/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/6/2023 Approved KEVIN BERBERYAN
Insulation 10/6/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 10/6/2023 Approved KEVIN BERBERYAN
Drywall Nailing 11/3/2023 Approved KEVIN BERBERYAN
Shower Pan 11/3/2023 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 11/7/2023 Approved KEVIN BERBERYAN
Shower Pan 11/7/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 11/17/2023 Approved KEVIN BERBERYAN
Shower Pan 11/17/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/4/2024 Corrections Issued MISAEL ESPARZA
Gas Test 3/4/2024 Corrections Issued MISAEL ESPARZA
Service/Power Release 3/4/2024 Not Ready for Inspection MISAEL ESPARZA
Final 4/11/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 4/11/2024 Approved KEVIN BERBERYAN
Green Building Final 4/11/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 4/11/2024 Approved KEVIN BERBERYAN
Final 4/19/2024 Partial Approval ROBERT GOLD
Final 5/20/2024 OK to Issue CofO KEVIN BERBERYAN