11738 N ANDREW AVE 91344
Certificate Information: 11738 N ANDREW AVE 91344
- Application / Permit
- 22014-20000-03907
- Plan Check / Job No.
- B22VN11429
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 9' X 30' ADDITION TO THE (E) SINGLE FAMILY DWELLING; CONVERSION OF A 22 SQ FT PORTION OF THE (E) ATTACHED GARAGE INTO LIVING AREA; INTERIOR REMODEL TO THE KITCHEN, LIVING, DINING AND BATHROOM AREAS AND THE CREATION OF LAUNDRY ROOM PER ENGINEERING.
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | OMAR GARNICA |
| Corrections Issued | 8/5/2022 | OMAR GARNICA |
| Building Plans Picked Up | 8/9/2022 | APPLICANT |
| Applicant returned to address corrections | 8/19/2022 | MINA HABILI |
| Plan Check Approved | 8/19/2022 | MINA HABILI |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 9/29/2023 | JAVIER RAMOS JR |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 8/8/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 8/18/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2022 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/19/2022 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 10/18/2022 | Conditional Approval | JAVIER RAMOS JR |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/18/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/31/2022 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 12/13/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/9/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/9/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 2/9/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 3/7/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/7/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 3/7/2023 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 3/10/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 3/20/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/6/2023 | Approved | JAVIER RAMOS JR |
| Final | 9/1/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/1/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/1/2023 | Approved | JACK KARGODORIAN |
| Final | 9/8/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 9/8/2023 | Approved | JAVIER RAMOS JR |