13065 W ADDISON ST 91423

Certificate Information: 13065 W ADDISON ST 91423

Application / Permit
22014-20000-03880
Plan Check / Job No.
B22VN11754
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
23'- 1" X 16' 8" ADDITION TO REAR OF (E) SFD AND MAJOR INTERIOR REMODEL TO REVISE ENTIRE FLOOR PLAN LAYOUT. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/11/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2022 APPLICANT
Assigned to Plan Check Engineer 8/3/2022 GURUNATH NESARAJAH
Corrections Issued 8/3/2022 GURUNATH NESARAJAH
Building Plans Picked Up 8/30/2022 APPLICANT
Plan Check Approved 10/3/2022 ANGELICA MARTINEZ
Issued 10/11/2022 APPLICANT
CofO in Progress 6/2/2023 KIRK SANDERS
Permit Finaled 6/7/2023 MICHAEL SMITH
CofO Issued 6/7/2023 MICHAEL SMITH
Permit Finaled 6/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/15/2022 LEE GUILBEAUX
ZA Case Cleared 8/16/2022 NATHAN ROMINE
Sewer availability Cleared 8/22/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/23/2022 Not Ready for Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 12/2/2022 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 12/8/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/8/2022 Partial Approval ARAM AVEDISIAN
Wood Frame 12/15/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/16/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved KIRK SANDERS
Green Building Rough 2/16/2023 Approved KIRK SANDERS
HVAC-Rough 2/16/2023 Corrections Issued KIRK SANDERS
Rough-Elec/Plmb/HVAC 2/16/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 2/23/2023 Partial Approval JOHN KIDWELL
Shower Pan 3/1/2023 Approved KIRK SANDERS
Insulation 3/6/2023 Approved JUAN VALENZUELA
Drywall Nailing 3/15/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/15/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/25/2023 Approved KIRK SANDERS
HVAC-Final 5/25/2023 Approved KIRK SANDERS
PLUMBING-Final 5/25/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 5/25/2023 Approved KIRK SANDERS
Final 6/1/2023 OK to Issue CofO KIRK SANDERS
Gas Test 6/1/2023 Approved KIRK SANDERS
Green Building Final 6/1/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 6/1/2023 Approved KIRK SANDERS