207 3/4 E 71ST ST 90003

Certificate Information: 207 3/4 E 71ST ST 90003

Application / Permit
22014-20000-03868
Plan Check / Job No.
B22VN11710
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/18/2022
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 DANIEL YIP
Corrections Issued 8/9/2022 DANIEL YIP
Plan Check Approved 8/17/2022 DANIEL YIP
Issued 8/18/2022 APPLICANT
CofO in Progress 9/22/2025 BRENDAN MORELLI
Permit Finaled 9/25/2025 DEROLD HAUFF
CofO Issued 9/25/2025 DEROLD HAUFF
Permit Finaled 9/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/11/2022 WALLIE JONG
Sewer availability Cleared 8/11/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/12/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/4/2023 Partial Approval MICHAEL LEWIS
Pre-Inspection 12/4/2023 Corrections Issued MICHAEL LEWIS
Underground Mechanical 12/4/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/12/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 12/18/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 10/1/2024 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 10/22/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 10/22/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 10/22/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 3/3/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/3/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/3/2025 Approved JOHN QUINTANILLA
Underground Mechanical 3/3/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/7/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Insulation 3/12/2025 Corrections Issued JOHN QUINTANILLA
Interior/Exterior Lathing 3/12/2025 Approved JOHN QUINTANILLA
Insulation 5/1/2025 Corrections Issued JOHN QUINTANILLA
Sewer 7/3/2025 No Access for Inspection JOHN QUINTANILLA
Sewer 7/24/2025 Approved JOHN QUINTANILLA
Drywall Nailing 8/21/2025 Approved BRENDAN MORELLI
Final 8/21/2025 Corrections Issued BRENDAN MORELLI
Smoke Detectors 8/21/2025 Approved BRENDAN MORELLI
Final 9/19/2025 OK to Issue CofO BRENDAN MORELLI