207 3/4 E 71ST ST 90003
Certificate Information: 207 3/4 E 71ST ST 90003
- Application / Permit
- 22014-20000-03868
- Plan Check / Job No.
- B22VN11710
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | DANIEL YIP |
| Corrections Issued | 8/9/2022 | DANIEL YIP |
| Plan Check Approved | 8/17/2022 | DANIEL YIP |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 9/22/2025 | BRENDAN MORELLI |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
| CofO Issued | 9/25/2025 | DEROLD HAUFF |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/11/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/4/2023 | Partial Approval | MICHAEL LEWIS |
| Pre-Inspection | 12/4/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 12/4/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/12/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/1/2024 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 10/22/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 10/22/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 3/3/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 3/3/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 3/3/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 3/3/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 3/12/2025 | Corrections Issued | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/12/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 5/1/2025 | Corrections Issued | JOHN QUINTANILLA |
| Sewer | 7/3/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Sewer | 7/24/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 8/21/2025 | Approved | BRENDAN MORELLI |
| Final | 8/21/2025 | Corrections Issued | BRENDAN MORELLI |
| Smoke Detectors | 8/21/2025 | Approved | BRENDAN MORELLI |
| Final | 9/19/2025 | OK to Issue CofO | BRENDAN MORELLI |