233 E 91ST ST 90003

Certificate Information: 233 E 91ST ST 90003

Application / Permit
22014-20000-03856
Plan Check / Job No.
B22VN11674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* ADDITION (340 SF) TO (E) 1-STORY SFD (1091 SF). ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 8/22/2022
Issuing Office
Current Status
CofO Issued on 10/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2022 APPLICANT
Assigned to Plan Check Engineer 8/1/2022 VIVIAN LAO
Corrections Issued 8/2/2022 VIVIAN LAO
Applicant returned to address corrections 8/9/2022 VIVIAN LAO
Plan Check Approved 8/16/2022 VIVIAN LAO
Issued 8/22/2022 APPLICANT
CofO in Progress 6/9/2023 STUART CHAPMAN
Permit Finaled 10/19/2023 DEROLD HAUFF
CofO Issued 10/19/2023 DEROLD HAUFF
Permit Finaled 10/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2022 JEANIE LAM
Sewer availability Cleared 8/12/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/15/2022 JEANIE LAM

Contact Information

Contractor Monroy M W Construction Inc; Lic. No.: 1066342-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 9/22/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 9/22/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Partial Approval LILIANA PORTILLO
Insulation 9/26/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/21/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/21/2022 Approved JOSEPH MCGARRY
HVAC-Rough 10/21/2022 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 10/21/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 10/21/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/26/2022 Conditional Approval LILIANA PORTILLO
Green Building Rough 10/26/2022 Approved LILIANA PORTILLO
HVAC-Rough 10/26/2022 Not Ready for Inspection LILIANA PORTILLO
Insulation 10/26/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 1/19/2023 Approved LILIANA PORTILLO
Drywall Nailing 1/19/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/19/2023 Approved LILIANA PORTILLO
Final 1/19/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/19/2023 Approved LILIANA PORTILLO
Green Building Final 1/19/2023 Approved LILIANA PORTILLO
HVAC-Final 1/19/2023 Approved LILIANA PORTILLO
PLUMBING-Final 1/19/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/19/2023 Approved LILIANA PORTILLO
Final 6/8/2023 OK to Issue CofO STUART CHAPMAN