13241 W OTSEGO ST 91423

Certificate Information: 13241 W OTSEGO ST 91423

Application / Permit
22014-20000-03852
Plan Check / Job No.
B22VN11666
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 18'2" X 3'6" & 7'5" X 20'2" AT 1ST FLOOR AND 15'1" X 20'2" 2ND FLOOR ADDITION & CONVERT (E) 18'2" X 20'2" TWO CAR GARAGE TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33. (C) AND (E), ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/19/2022 RARES BODEA
Corrections Issued 8/29/2022 RARES BODEA
Quality Review Completed 9/13/2022 STEVEN KIM
Building Plans Picked Up 9/14/2022 APPLICANT
Plan Check Approved 1/5/2024 RARES BODEA
Issued 1/19/2024 APPLICANT
CofO in Progress 5/9/2025 GAREN HAYRAPETYAN
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/16/2023 LUCIA MERCADO
Sewer availability Cleared 3/16/2023 LUCIA MERCADO
Low Impact Development Cleared 12/8/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 12/28/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/5/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2024 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 3/18/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/18/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 3/28/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/23/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 5/29/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/29/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/29/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/29/2024 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 5/30/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/7/2024 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 6/7/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/7/2024 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/18/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 6/18/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Approved WILLIAM WREN
Green Building Rough 6/18/2024 Approved WILLIAM WREN
Insulation 7/1/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/1/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 7/1/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/11/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/11/2024 Approved SALVADOR MARTINEZ
Final 2/6/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/6/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/6/2025 Approved GAREN HAYRAPETYAN
Final 4/23/2025 Corrections Issued OGANES TARAKHCHYAN
Final 5/9/2025 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 5/9/2025 Approved GAREN HAYRAPETYAN