321 E 74TH ST 90003

Certificate Information: 321 E 74TH ST 90003

Application / Permit
22014-20000-03833
Plan Check / Job No.
B22VN11615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 DANIEL YIP
Corrections Issued 8/9/2022 DANIEL YIP
Applicant returned to address corrections 10/19/2022 PRANITA SHAH
Applicant returned to address corrections 10/27/2022 DANIEL YIP
Plan Check Approved 11/2/2022 PRANITA SHAH
Issued 12/2/2022 APPLICANT
CofO in Progress 9/13/2023 MICHAEL LEWIS
Permit Finaled 9/21/2023 DEROLD HAUFF
CofO Issued 9/21/2023 DEROLD HAUFF
Permit Finaled 9/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/12/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/15/2022 JEANIE LAM
Sewer availability Cleared 8/15/2022 JEANIE LAM
Construction near power lines Cleared 8/17/2022 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 10/18/2022 HELEN JADALI
Low Impact Development Cleared 11/1/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/1/2022 TREVOR QUAN

Contact Information

Architect Sabet,, Golnarges M; Lic. No.: NA33474       ,
Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2022 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 12/13/2022 No Access for Inspection LILIANA PORTILLO
Pre-Inspection 12/13/2022 No Access for Inspection LILIANA PORTILLO
PLUMBING-Rough 12/30/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/3/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 1/7/2023 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 1/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/20/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/25/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 3/2/2023 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/7/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval ALIZAH MAYAGOITIA
Gas Test 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 3/7/2023 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 3/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/13/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 3/13/2023 Corrections Issued LILIANA PORTILLO
Sewer 3/13/2023 Approved LILIANA PORTILLO
Underground Mechanical 3/13/2023 Corrections Issued LILIANA PORTILLO
Wood Frame 3/13/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/20/2023 Approved LILIANA PORTILLO
HVAC-Rough 3/20/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 3/20/2023 Approved LILIANA PORTILLO
Underground Mechanical 3/20/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/29/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/29/2023 Partial Approval LILIANA PORTILLO
Green Building Rough 3/29/2023 Approved LILIANA PORTILLO
HVAC-Rough 3/29/2023 Approved LILIANA PORTILLO
Insulation 3/31/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/31/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 4/6/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/18/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/9/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 6/9/2023 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 7/20/2023 Corrections Issued MICHAEL LEWIS
HVAC-Final 7/20/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 7/20/2023 Corrections Issued MICHAEL LEWIS
Final 8/31/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 8/31/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 8/31/2023 Approved MICHAEL LEWIS
Final 9/11/2023 OK to Issue CofO MICHAEL LEWIS
HVAC-Final 9/11/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Approved MICHAEL LEWIS