8039 W GROVE ST 91040

Certificate Information: 8039 W GROVE ST 91040

Application / Permit
22014-20000-03832
Plan Check / Job No.
B22VN11613
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan interior remodeling and a 205.2 sq. ft. addition to existing single story SFD
Permit Issued
Issued on 10/22/2022
Issuing Office
Current Status
CofO Issued on 8/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/1/2022 SUNMIN LEE
Corrections Issued 8/2/2022 SUNMIN LEE
Applicant returned to address corrections 10/7/2022 SUNMIN LEE
Applicant returned to address corrections 10/17/2022 SUNMIN LEE
Plan Check Approved 10/21/2022 SUNMIN LEE
Issued 10/22/2022 APPLICANT
CofO in Progress 7/12/2023 MATTHEW NELSON
Permit Finaled 8/4/2023 RUBEN SALAS
CofO Issued 8/4/2023 RUBEN SALAS
Permit Finaled 8/4/2023 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/19/2022 KIRK LINKLATER
Miscellaneous Cleared 10/5/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 10/7/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/7/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/18/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/21/2022 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 11/29/2022 Approved WILLIAM WREN
PLUMBING-Rough 12/28/2022 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 1/31/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 1/31/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval WILLIAM WREN
HVAC-Rough 1/31/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 1/31/2023 Approved WILLIAM WREN
Shower Pan 1/31/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/8/2023 Approved MATTHEW NELSON
HVAC-Rough 2/8/2023 Approved MATTHEW NELSON
Insulation 2/22/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 2/22/2023 Partial Approval WILLIAM WREN
Drywall Nailing 3/8/2023 Approved WILLIAM WREN
Final 6/30/2023 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 6/30/2023 Approved WILLIAM WREN
Final 7/11/2023 OK to Issue CofO MATTHEW NELSON