8825 N LEMONA AVE 91343
Certificate Information: 8825 N LEMONA AVE 91343
- Application / Permit
- 22014-20000-03816
- Plan Check / Job No.
- B22VN11553
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 33'-4" X 22'-3" IRREG SHAPED ADDITION TO AND CONVERT (E) 20' X 22'2" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERIG.
- Permit Issued
- Issued on 10/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 8/2/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/9/2022 | APPLICANT |
| Plan Check Approved | 9/26/2022 | OMAR GARNICA |
| Issued | 10/7/2022 | APPLICANT |
| CofO in Progress | 5/15/2023 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 5/16/2023 | MICHAEL SMITH |
| CofO Issued | 5/16/2023 | MICHAEL SMITH |
| Permit Finaled | 5/16/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/9/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Ea Constructions Inc; Lic. No.: 1096892-B | 14695 PARTHENIA ST APT 112 PANORAMA CITY, CA 91402 |
| Engineer | Yu,, Jennifer Arianna; Lic. No.: C79156 | 3828 EARLE AVE ROSEMEAD, CA 91770 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | WILLIAM WREN |
| Deputy Drilled-In Anchors | 11/3/2022 | Conditional Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/8/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/8/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/8/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 11/15/2022 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/16/2022 | Approved | GREGG CUMMINGS |
| Sewer | 11/22/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 11/22/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 1/25/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/3/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/10/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 2/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/15/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/15/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 2/17/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/22/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/22/2023 | Approved | GREGG CUMMINGS |
| Insulation | 2/27/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/27/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/3/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 3/3/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/3/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 4/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/28/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/4/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/4/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 5/4/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/15/2023 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |