6252 N CARTWRIGHT AVE 91606
Certificate Information: 6252 N CARTWRIGHT AVE 91606
- Application / Permit
- 22014-20000-03803
- Plan Check / Job No.
- B22VN11531
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New one story accessory dwelling unit attached to existing 2-car garage ADU per ordinance LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 10/24/2023
- Issuing Office
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JAD BASMA |
| Corrections Issued | 10/27/2022 | JAD BASMA |
| Quality Review Completed | 11/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/18/2023 | JAD BASMA |
| Applicant returned to address corrections | 8/9/2023 | JAD BASMA |
| Applicant returned to address corrections | 9/7/2023 | JAD BASMA |
| Applicant returned to address corrections | 9/13/2023 | JAD BASMA |
| Plan Check Approved | 10/20/2023 | JAD BASMA |
| Issued | 10/24/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
| CofO Issued | 7/31/2024 | RUBEN SALAS |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 12/5/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 2/13/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/5/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 9/6/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Future Builders & Design Inc; Lic. No.: 1058468-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/6/2023 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 11/6/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 11/7/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/28/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 11/28/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/28/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/28/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/30/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/30/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/30/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 12/7/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/8/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/13/2023 | Conditional Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 12/14/2023 | No Access for Inspection | JOHN HAYES |
| Insulation | 12/18/2023 | Conditional Approval | THOMAS FINNILA |
| Insulation | 12/20/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/20/2023 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 12/27/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/27/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 6/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 6/21/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 6/21/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/18/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |