6252 N CARTWRIGHT AVE 91606

Certificate Information: 6252 N CARTWRIGHT AVE 91606

Application / Permit
22014-20000-03803
Plan Check / Job No.
B22VN11531
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New one story accessory dwelling unit attached to existing 2-car garage ADU per ordinance LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 10/24/2023
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 JAD BASMA
Corrections Issued 10/27/2022 JAD BASMA
Quality Review Completed 11/2/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/18/2023 JAD BASMA
Applicant returned to address corrections 8/9/2023 JAD BASMA
Applicant returned to address corrections 9/7/2023 JAD BASMA
Applicant returned to address corrections 9/13/2023 JAD BASMA
Plan Check Approved 10/20/2023 JAD BASMA
Issued 10/24/2023 APPLICANT
CofO in Progress 7/19/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 7/31/2024 RUBEN SALAS
CofO Issued 7/31/2024 RUBEN SALAS
Permit Finaled 7/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/8/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 12/5/2022 ROMAN GUTIERREZ
Sewer availability Cleared 12/5/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 2/13/2023 RIDWAN HARDY
Low Impact Development Cleared 9/5/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 9/6/2023 ROMAN GUTIERREZ

Contact Information

Contractor Future Builders & Design Inc; Lic. No.: 1058468-B       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/6/2023 Not Ready for Inspection JOHN HAYES
Underground Mechanical 11/6/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 11/7/2023 Approved JOHN HAYES
Footing/Foundation/Slab 11/7/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/28/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 11/28/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/28/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 11/28/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 11/30/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 11/30/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 11/30/2023 Approved OGANES TARAKHCHYAN
Shower Pan 12/7/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/8/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/13/2023 Conditional Approval KEVIN BERBERYAN
Deputy Drilled-In Anchors 12/14/2023 No Access for Inspection JOHN HAYES
Insulation 12/18/2023 Conditional Approval THOMAS FINNILA
Insulation 12/20/2023 Approved JOHN HAYES
Interior/Exterior Lathing 12/20/2023 Partial Approval JOHN HAYES
Drywall Nailing 12/27/2023 Approved JOHN HAYES
Interior/Exterior Lathing 12/27/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 6/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/15/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/15/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 7/18/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Gas Test 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ