23100 W STRATHERN ST 91304

Certificate Information: 23100 W STRATHERN ST 91304

Application / Permit
22014-20000-03776
Plan Check / Job No.
B22VN11457
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 1.5' x 6' TO EXTEND THE BATHROOM, AND INTERIOR ALTERATION TO CONVERT THE RESIDENCE FROM THREE BEDROOMS, TWO BATHROOMS TO TWO BEDROOMS, ONE BATHROOM AND A LAUNDRY ROOM.
Permit Issued
Issued on 7/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 7/26/2022 LUIS RINCON
Plan Check Approved 7/26/2022 LUIS RINCON
Issued 7/26/2022 APPLICANT
CofO in Progress 8/31/2022 MORRIS JACKSON
Permit Finaled 9/1/2022 JOHN JANSON
CofO Issued 9/1/2022 JOHN JANSON
Permit Finaled 9/1/2022 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/28/2022 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 8/1/2022 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 8/4/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/4/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/10/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 8/10/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 8/10/2022 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 8/10/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/16/2022 Approved JUSTIN HAWLEY
Shower Pan 8/16/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 8/22/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/22/2022 Approved CHRIS CHRISTENSEN
Final 8/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/22/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/22/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 8/22/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 8/30/2022 Approved MORRIS JACKSON
Final 8/30/2022 OK to Issue CofO MORRIS JACKSON
HVAC-Final 8/30/2022 Approved MORRIS JACKSON
PLUMBING-Final 8/30/2022 Approved MORRIS JACKSON