10346-10348 N MATHER AVE 91040
Certificate Information: 10346-10348 N MATHER AVE 91040
- Application / Permit
- 22014-20000-03766
- Plan Check / Job No.
- B22VN11426
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Addition to existing garage and convert garage to New Accessory Dwelling Unit
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | PRANITA SHAH |
| Corrections Issued | 8/8/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 9/19/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 9/21/2022 | PRANITA SHAH |
| Plan Check Approved | 10/16/2022 | PRANITA SHAH |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 4/29/2024 | DAVID ANDERSON |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
| CofO Issued | 5/15/2024 | RUBEN SALAS |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | JOSE DUARTE-DIAZ |
| Watercourse | Cleared | 8/17/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/18/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 8/30/2022 | KIRK LINKLATER |
| ZI | Cleared | 9/6/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: NA79415 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 2/8/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 2/13/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 2/22/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/14/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/16/2023 | Not Ready for Inspection | WILLIAM WREN |
| Gas Test | 5/16/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 7/11/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 7/11/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/18/2023 | Partial Approval | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/10/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/18/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/6/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/6/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/6/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/6/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/7/2023 | Approved | DAVID ANDERSON |
| Insulation | 9/14/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 10/2/2023 | Corrections Issued | DAVID ANDERSON |
| Drywall Nailing | 11/1/2023 | Approved | DAVID ANDERSON |
| Insulation | 11/1/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 11/1/2023 | Approved | DAVID ANDERSON |
| Final | 3/19/2024 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 3/19/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/26/2024 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 4/26/2024 | Approved | DAVID ANDERSON |