7714-7716 N FAUST AVE 91304
Certificate Information: 7714-7716 N FAUST AVE 91304
- Application / Permit
- 22014-20000-03764
- Plan Check / Job No.
- B22VN11423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan CONVERTING EXISTING ATTACHED GARAGE TO ADU PER CA GOVT. CODE 65852.2(e)(1)(A). CONSTRUCTION AND FRAMING PER WFPP
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2022 | HANS SANTIAGO |
| Corrections Issued | 8/2/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/9/2022 | HANS SANTIAGO |
| Plan Check Approved | 8/24/2022 | ANDREW SANTIAGO |
| No Progress | 8/25/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 8/25/2022 | ANDREW SANTIAGO |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | PETER FOLLING |
| CofO in Progress | 2/2/2023 | PETER FOLLING |
| CofO in Progress | 2/2/2023 | PETER FOLLING |
| Permit Finaled | 2/15/2023 | JOHN JANSON |
| CofO Issued | 2/15/2023 | JOHN JANSON |
| Permit Finaled | 2/15/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Ec1 Builders Inc; Lic. No.: 1075811-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/14/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/20/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/20/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/12/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/12/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 10/12/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/19/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/19/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/19/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 10/19/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/25/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/25/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/25/2022 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 11/1/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Insulation | 11/1/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/8/2022 | Approved | TROY SANDERS |
| Gas Test | 11/8/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/30/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 12/5/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Pre-Inspection | 12/8/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Final | 1/30/2023 | Partial Approval | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 1/30/2023 | Approved | PETER FOLLING |
| Final | 2/2/2023 | OK to Issue CofO | PETER FOLLING |