8051 N LULLABY LANE 91402
Certificate Information: 8051 N LULLABY LANE 91402
- Application / Permit
- 22014-20000-03763
- Plan Check / Job No.
- B22VN11422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan ADD 42'-7" X 23'-10" IRREGULAR SHAPE TO AND CONVERT EXISTING DETACHED GARGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/1/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 11/15/2022 | SELLA BENYAMIN |
| Plan Check Approved | 11/20/2022 | SELLA BENYAMIN |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 6/12/2025 | VINCENT HANLEY |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/27/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/31/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/14/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/8/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 8/8/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/8/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/27/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 8/27/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/20/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 9/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/20/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/23/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 9/23/2024 | Conditional Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/23/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/27/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/9/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/9/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 10/9/2024 | Approved | VINCENT HANLEY |
| Gas Test | 12/6/2024 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 12/6/2024 | Approved | LOUIS ESCOTO |
| Final | 4/15/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/15/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 4/15/2025 | Approved | MISAEL ESPARZA |
| Final | 4/22/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Final | 4/28/2025 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Approved | VINCENT HANLEY |
| Wood Frame | 5/5/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/2/2025 | Approved | VINCENT HANLEY |
| Final | 6/2/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 6/2/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/2/2025 | Approved | VINCENT HANLEY |
| Final | 6/12/2025 | OK to Issue CofO | VINCENT HANLEY |