5730 S 6TH AVE 90043
Certificate Information: 5730 S 6TH AVE 90043
- Application / Permit
- 22014-20000-03667
- Plan Check / Job No.
- B22VN11159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (N) 9'-6" X 10' ON FIRST FLOOR TO (E) GARAGE AND CONVERT ENTIRE 45' X 13'-6" BUILDING TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/18/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/23/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 8/10/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 8/18/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 11/20/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 12/12/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | BARRY HACHE |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
| CofO Issued | 12/14/2024 | DEROLD HAUFF |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/18/2022 | ROGELIO CORTES |
| Address approval | Cleared | 12/6/2022 | ABEL CASILLAS |
| Miscellaneous | Cleared | 3/22/2023 | ANACANY HURTADO |
| Construction near power lines | Cleared | 7/10/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/10/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 8/10/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/10/2023 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 10/28/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Stewart,, Carl; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2023 | Partial Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 1/17/2024 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 1/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 1/19/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 3/6/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/1/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | No Access for Inspection | MICHAEL LEWIS |
| Wood Frame | 4/18/2024 | No Access for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 5/21/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/21/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 5/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/22/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 5/22/2024 | Approved | ANTHONY EGSON |
| Insulation | 5/30/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 5/31/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 6/6/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/6/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/10/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/12/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 6/21/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/25/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 6/25/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/25/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/12/2024 | Approved | AMIR NAZARIAN |
| Final | 9/12/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 9/12/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 9/12/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 10/16/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/16/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Approved | ANTHONY EGSON |
| Final | 10/30/2024 | Corrections Issued | BARRY HACHE |
| Final | 11/5/2024 | Conditional Approval | BARRY HACHE |
| Service/Power Release | 11/5/2024 | Approved | BARRY HACHE |
| Final | 11/18/2024 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/25/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 11/25/2024 | Corrections Issued | BARRY HACHE |
| Grounding or Bonding | 11/25/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/12/2024 | OK to Issue CofO | BARRY HACHE |