6259 N DENNY AVE 91606
Certificate Information: 6259 N DENNY AVE 91606
- Application / Permit
- 22014-20000-03653
- Plan Check / Job No.
- B22VN11133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 19'-5" X 9'-1" PORTION OF DWELLING TO DETACH GARAGE FROM DWELLING; ADD 22' X 16'-5' IRREGULAR SHAPED TO THE FRONT OF THE DWELLING; ADD 23'X 5'-6" AND 26'-8" X 14'-8" IRREGULAR SHAPED TO REAR AND SIDE OF DWELLING; INTERIOR REMODEL
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/25/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | SELLA BENYAMIN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 9/30/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
| CofO Issued | 10/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/11/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/12/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 5/9/2023 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 5/31/2023 | Approved | JOHN HAYES |
| Wood Frame | 5/31/2023 | Approved | JOHN HAYES |
| Insulation | 6/7/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | No Access for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 9/14/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/12/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 10/16/2023 | No Access for Inspection | JOHN HAYES |
| HVAC-Rough | 10/16/2023 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/25/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/8/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 11/21/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 11/21/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 8/23/2024 | Corrections Issued | JOSE AVILA |
| Final | 8/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/20/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |