7807 N ZOMBAR AVE 91406
Certificate Information: 7807 N ZOMBAR AVE 91406
- Application / Permit
- 22014-20000-03628
- Plan Check / Job No.
- B22VN11099
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel (E) 1-story SFD w/ att Garage
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2022 | MINA HABILI |
| Corrections Issued | 7/21/2022 | MINA HABILI |
| Plan Check Approved | 8/18/2022 | MINA HABILI |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 1/10/2025 | VINCENT HANLEY |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/25/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/26/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | M D R N Remodeling Company; Lic. No.: 1065843-B | , |
| Contractor | Mdrn Construction; Lic. No.: 1065843-B | , |
| Engineer | Kyupelyan,, Emil; Lic. No.: C91238 | 8045 LASAINE AVE NORTHRIDGE, CA 91325 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2022 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 10/11/2022 | Corrections Issued | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 10/12/2022 | Conditional Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/18/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/7/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | GREGG CUMMINGS |
| Insulation | 11/21/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/16/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 12/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 12/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 1/12/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/8/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 5/8/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 5/8/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 7/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 7/11/2023 | Approved | GREGG CUMMINGS |
| Final | 10/24/2023 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/9/2025 | Approved | VINCENT HANLEY |
| Final | 1/9/2025 | OK to Issue CofO | VINCENT HANLEY |