8756 N RANCHITO AVE 91402
Certificate Information: 8756 N RANCHITO AVE 91402
- Application / Permit
- 22014-20000-03622
- Plan Check / Job No.
- B22VN11094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan (E) Den conversion to master bedroom, bath, closet and family room addition (246 s.f). Work per WFPP
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | ADAM HEGAZI |
| Corrections Issued | 7/25/2022 | ADAM HEGAZI |
| Plan Check Approved | 8/18/2022 | ADAM HEGAZI |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 7/25/2024 | GREGG CUMMINGS |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
| CofO Issued | 8/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/5/2022 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 8/9/2022 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 2/14/2024 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 2/20/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 3/13/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 4/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 4/19/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/23/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/23/2024 | Approved | GREGG CUMMINGS |
| Sewer | 4/23/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/29/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/29/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/29/2024 | Approved | MICHEL ABAJAN |
| Wood Frame | 4/29/2024 | Partial Inspection | MICHEL ABAJAN |
| Wood Frame | 5/2/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 5/6/2024 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/8/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/17/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/17/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/17/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | GREGG CUMMINGS |
| Insulation | 5/20/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/24/2024 | Approved | JOHN COLEMAN |
| Final | 7/19/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/19/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 7/19/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 7/19/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 7/24/2024 | Approved | GREGG CUMMINGS |
| Final | 7/24/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 7/24/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 7/24/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/24/2024 | Approved | GREGG CUMMINGS |