4355-4357 N LANAI ROAD 91436
Certificate Information: 4355-4357 N LANAI ROAD 91436
- Application / Permit
- 22014-20000-03617
- Plan Check / Job No.
- B22VN11080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW 21'-3" x 31'-6" ACCESSORY DWELLING UNIT ABOVE (E) ATT. 2-CAR GARAGE (PER LAMC 12.22 A.33(c) and (e)), AND DEMO (E) STORAGE AND ADD NEW 8' x 10'-11" STORAGE ROOM; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/5/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/5/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/10/2022 | APPLICANT |
| Plan Check Approved | 10/17/2022 | SEAN SHAHMIRI |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 12/28/2023 | VINCENT HANLEY |
| No Progress | 1/4/2024 | SEAN WIRCH |
| CofO in Progress | 3/28/2024 | VINCENT HANLEY |
| CofO in Progress | 3/28/2024 | VINCENT HANLEY |
| Permit Finaled | 4/2/2024 | JOHN JANSON |
| CofO Issued | 4/2/2024 | JOHN JANSON |
| Permit Finaled | 4/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Miscellaneous | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Private street | Cleared | 8/17/2022 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 8/17/2022 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 9/2/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 9/25/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: C53434 | 3814 VANALDEN AVE TARZANA, CA 91356 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2023 | Approved | VINCENT HANLEY |
| Pre-Inspection | 1/13/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/13/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/13/2023 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/27/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/27/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/27/2023 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/27/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/8/2023 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/8/2023 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/13/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/21/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/21/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/21/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/21/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/21/2023 | Approved | VINCENT HANLEY |
| Insulation | 4/26/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/1/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/5/2023 | Partial Approval | VINCENT HANLEY |
| Final | 10/26/2023 | Corrections Issued | SEAN WIRCH |
| Green Building Final | 10/26/2023 | Not Ready for Inspection | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Not Ready | SEAN WIRCH |
| Smoke Detectors | 10/26/2023 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 11/8/2023 | Approved | VINCENT HANLEY |
| Final | 11/8/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 11/8/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/8/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/8/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | VINCENT HANLEY |
| Final | 12/28/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 3/28/2024 | OK to Issue CofO | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Approved | VINCENT HANLEY |