6915 N ALCOVE AVE 91605

Certificate Information: 6915 N ALCOVE AVE 91605

Application / Permit
22014-20000-03602
Plan Check / Job No.
B22VN11047
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 29'-6" X 20'10" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TO EXISTING DETACHED GARAGE
Permit Issued
Issued on 5/1/2023
Issuing Office
Valley
Current Status
Issued on 5/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 SELLA BENYAMIN
Corrections Issued 9/1/2022 SELLA BENYAMIN
Quality Review Completed 9/9/2022 STEVEN KIM
Building Plans Picked Up 9/14/2022 APPLICANT
Plan Check Approved 4/25/2023 SELLA BENYAMIN
Issued 5/1/2023 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 9/1/2022 WALTER RAMIREZ
Address approval Cleared 10/26/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/9/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/9/2023 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/14/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/14/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Yogurtian,, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2024 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 6/10/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 6/10/2024 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 6/14/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/7/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/7/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/31/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/31/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/2/2024 Approved GAREN HAYRAPETYAN
Green Building Rough 12/2/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/2/2024 Approved GAREN HAYRAPETYAN
Insulation 12/6/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/11/2024 Approved OGANES TARAKHCHYAN
Shower Pan 1/29/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 2/11/2025 Approved MICHAEL CORTEZ
Shower Pan 2/11/2025 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Rough 5/28/2025 Approved GAREN HAYRAPETYAN
Gas Test 5/28/2025 Approved GAREN HAYRAPETYAN
Sewer 5/28/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/28/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 10/20/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 10/20/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 10/20/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 12/5/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 12/5/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 12/5/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Rough 12/5/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 12/10/2025 Approved WAYNE REGESTER
HVAC-Final 12/10/2025 Approved WAYNE REGESTER
Service/Power Release 12/10/2025 Approved WAYNE REGESTER