4547 N MATILIJA AVE 91423

Certificate Information: 4547 N MATILIJA AVE 91423

Application / Permit
22014-20000-03560
Plan Check / Job No.
B22VN10913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
25'-1" X 28'-8" IRREGUALR SHAPED ADDITION TO AND CONVERSION OF EXISTING 16'-2" X 28'-8" RECREATION ROOM INTO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - ALL WORK PER ENGINEER
Permit Issued
Issued on 10/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 DANIEL ABRAMYAN
Corrections Issued 7/16/2022 DANIEL ABRAMYAN
Building Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 7/28/2022 JEROME MAGAT PALMA
Plan Check Approved 10/12/2022 HAYATO TSUCHIYA
Issued 10/13/2022 APPLICANT
CofO in Progress 11/13/2023 MISAEL ESPARZA
Permit Finaled 12/8/2023 RUBEN SALAS
CofO Issued 12/8/2023 RUBEN SALAS
Permit Finaled 12/8/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/8/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/8/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/8/2022 COLIN LOREDO
Sewer availability Cleared 8/8/2022 COLIN LOREDO
ZI Cleared 8/19/2022 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2022 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 11/29/2022 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/7/2022 Approved MISAEL ESPARZA
Deputy Wood Construction 1/18/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 1/23/2023 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 1/26/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval MISAEL ESPARZA
Wood Frame 1/30/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/23/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/23/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 2/23/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 2/23/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/3/2023 Conditional Approval THOMAS FINNILA
Green Building Rough 4/3/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 4/3/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/3/2023 Approved THOMAS FINNILA
HVAC-Rough 4/11/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/11/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/26/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/26/2023 Approved MATTHEW NELSON
Green Building Rough 4/26/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/26/2023 Approved MATTHEW NELSON
Insulation 5/9/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/9/2023 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 6/8/2023 Approved JOHN COLEMAN
ELECTRICAL-Rough 7/11/2023 Partial Approval THOMAS FINNILA
Final 11/1/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/1/2023 Approved MISAEL ESPARZA
Green Building Final 11/1/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 11/1/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 11/1/2023 Approved MISAEL ESPARZA
Final 11/8/2023 OK to Issue CofO MISAEL ESPARZA
Green Building Final 11/8/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/8/2023 Approved MISAEL ESPARZA