846 E 104TH ST 90002

Certificate Information: 846 E 104TH ST 90002

Application / Permit
22014-20000-03534
Plan Check / Job No.
B22VN10848
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 32' X 20' (625 SQ FT) ADDITION OF TWO NEW BEDROOMS AND A BATHROOM TO THE REAR OF THE (E) SFD PER WFPP.
Permit Issued
Issued on 9/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 ALEC MOUSAKHANIAN
Corrections Issued 7/16/2022 ALEC MOUSAKHANIAN
Building Plans Picked Up 7/20/2022 APPLICANT
Plan Check Approved 9/29/2022 ALEC MOUSAKHANIAN
Issued 9/29/2022 APPLICANT
CofO in Progress 5/3/2023 JAMES CHAVEZ
Permit Finaled 5/10/2023 DANIEL ORRANTE
CofO Issued 5/10/2023 DANIEL ORRANTE
Permit Finaled 5/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/20/2022 SHASHA YU
ZI Cleared 7/20/2022 SHASHA YU
Eng Process Fee Ord 176,300 Cleared 8/3/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 9/22/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/26/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 9/28/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2022 Approved ALIZAH MAYAGOITIA
Pre-Inspection 10/5/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval RYAN SALAZAR
Insulation 10/13/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 10/13/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/15/2022 Corrections Issued JOHN KLARIN
Green Building Rough 11/15/2022 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 11/15/2022 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved JOHN KLARIN
Insulation 11/30/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/30/2022 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 11/30/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 12/9/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 12/9/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/17/2023 Approved JOHN KLARIN
Final 2/17/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 2/17/2023 Approved JOHN KLARIN
Green Building Final 2/17/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 2/17/2023 Approved JOHN KLARIN
Final 3/21/2023 Corrections Issued JOHN KLARIN
Final 4/5/2023 OK to Issue CofO JAMES CHAVEZ