2326 S LOUELLA AVE 90291
Certificate Information: 2326 S LOUELLA AVE 90291
- Application / Permit
- 22014-20000-03523
- Plan Check / Job No.
- B22VN10807
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL INT AND EXT WALLS EXCEPT FOR 2 FRONT WALLS AND ERECT AN IRR. SHAPED 33'-6 1/4" x 70'-1" TWO-STORY SINGLE FAMILY DWELLING WITH ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/2/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/5/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/5/2022 | APPLICANT |
| Plan Check Approved | 8/25/2022 | SEAN SHAHMIRI |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 8/17/2023 | HERBERT GIRON |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
| CofO Issued | 8/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 8/8/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 8/11/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 8/12/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/12/2022 | STEVEN JIN |
| Trees in Parkway | Cleared | 8/19/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Zepeda Juan; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/4/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 11/8/2022 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 11/18/2022 | Approved | DAVID FEILER |
| Deputy Steel/Welding | 11/30/2022 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Corrections Issued | EVAN COOPER |
| Wood Frame | 1/13/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 3/3/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 3/3/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/3/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/7/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 3/10/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/10/2023 | Partial Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 4/7/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 4/11/2023 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 4/11/2023 | Approved | HERBERT GIRON |
| Insulation | 4/14/2023 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 4/21/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/23/2023 | Approved | EVAN COOPER |
| Shower Pan | 5/30/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/7/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 8/7/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 8/8/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 8/8/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/9/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/9/2023 | Approved | HERBERT GIRON |
| Final | 8/17/2023 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 8/17/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 8/17/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 8/17/2023 | Approved | HERBERT GIRON |