8807-8809 N REMICK AVE 91352
Certificate Information: 8807-8809 N REMICK AVE 91352
- Application / Permit
- 22014-20000-03521
- Plan Check / Job No.
- B22VN10805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan New 2nd story addition on top of attached garage and convert to ADU per LAMC 12.22A.33(c) and (e)
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO Issued on 12/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 8/23/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 1/24/2023 | MARCELA FRANQUEZ |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 10/5/2023 | DAVID ANDERSON |
| No Progress | 12/4/2023 | DAVID MATSON |
| CofO in Progress | 12/20/2023 | DAVID MATSON |
| Permit Finaled | 12/20/2023 | RUBEN SALAS |
| CofO Issued | 12/20/2023 | RUBEN SALAS |
| Permit Finaled | 12/20/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/14/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/6/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | COLIN LOREDO |
| Hold | Cleared | 2/1/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/6/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 4/7/2023 | Approved | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 4/17/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Wood Construction | 4/18/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/18/2023 | Approved | MATTHEW NELSON |
| METHANE-Barrier | 4/18/2023 | Approved | MATTHEW NELSON |
| METHANE-Subgrade | 4/18/2023 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 5/1/2023 | Conditional Approval | DAVID MATSON |
| Pre-Inspection | 5/2/2023 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/7/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/7/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/7/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/7/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 6/7/2023 | Approved | MATTHEW NELSON |
| Insulation | 6/12/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/16/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/16/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | DAVID ANDERSON |
| Final | 9/27/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 9/27/2023 | Approved | DAVID ANDERSON |
| MERV13>=Final | 9/27/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 9/27/2023 | Approved | DAVID ANDERSON |
| METHANE-Final | 9/27/2023 | Approved | DAVID ANDERSON |
| METHANE-Rough | 9/27/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 9/27/2023 | Approved | DAVID ANDERSON |
| Final | 10/4/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | DAVID ANDERSON |