6309 N TAMPA AVE 91335
Certificate Information: 6309 N TAMPA AVE 91335
- Application / Permit
- 22014-20000-03518
- Plan Check / Job No.
- B22VN10801
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED 2-STORY ADU ADDITION ATTACHED TO THE GARAGE
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Current Status
- CofO Corrected on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | JAD BASMA |
| Corrections Issued | 8/18/2022 | JAD BASMA |
| Quality Review Completed | 8/30/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/20/2022 | JAD BASMA |
| Applicant returned to address corrections | 4/26/2023 | JAD BASMA |
| Plan Check Approved | 5/24/2023 | JAD BASMA |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 12/31/2024 | ALEXANDER HANDY |
| Re-Activate Permit | 1/16/2025 | JOHN JANSON |
| CofO Issued-Status Void | 1/16/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 1/16/2025 | JOHN JANSON |
| Permit Finaled | 1/16/2025 | JOHN JANSON |
| CofO Corrected | 1/16/2025 | JOHN JANSON |
| Permit Finaled | 1/16/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 10/24/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/26/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 11/2/2022 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/6/2023 | Not Ready for Inspection | HORACE FULTZ |
| Deputy Drilled-In Anchors | 7/25/2023 | Conditional Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 7/26/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/1/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 10/27/2023 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 10/31/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/29/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 11/29/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 12/1/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/6/2023 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 12/6/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/26/2023 | Approved | ALEXANDER HANDY |
| Insulation | 1/5/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 1/5/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/19/2024 | Approved | ALEXANDER HANDY |
| Final | 4/1/2024 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/1/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 4/1/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 4/1/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 4/1/2024 | Approved | ALEXANDER HANDY |
| Final | 5/29/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 5/29/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 5/29/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 12/30/2024 | Approved | ALEXANDER HANDY |
| Final | 12/30/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 12/30/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 12/30/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 12/30/2024 | Approved | ALEXANDER HANDY |