ePlan Convert existing 2-Car Garage, plus addition into ADU PER LAMC 12.22 A.33 (c)-(d) "The LID clearance has been deferred. Approval for LID requirements shall be obtained form LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 10/7/2022
Issuing Office
Current Status
CofO Issued on 5/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2022 APPLICANT
Assigned to Plan Check Engineer 7/25/2022 RACHEL BEYENE
Corrections Issued 7/25/2022 RACHEL BEYENE
Applicant returned to address corrections 9/19/2022 ADAM HEGAZI
Plan Check Approved 10/3/2022 RAHEL BEYENE
Issued 10/7/2022 APPLICANT
CofO in Progress 4/1/2024 JAVIER RAMOS JR
Permit Finaled 5/2/2024 RUBEN SALAS
CofO Issued 5/2/2024 RUBEN SALAS
Permit Finaled 5/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/4/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 8/4/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/24/2022 WALTER RAMIREZ
Grading Pre-Inspection Cleared 8/30/2022 VASIL MIHALEV
Roof/Waste drainage to street Cleared 9/22/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/17/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 3/9/2023 Approved ARAM AVEDISIAN
Deputy Wood Construction 3/21/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 3/24/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Corrections Issued JAVIER RAMOS JR
Special/Order Compliance 4/19/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/1/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 5/1/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 5/1/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 5/1/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 5/3/2023 Partial Approval MICHEL ABAJAN
Insulation 5/12/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 5/18/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 5/18/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Approved JAVIER RAMOS JR
Green Building Rough 5/18/2023 Approved JAVIER RAMOS JR
Insulation 5/18/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/18/2023 Approved JAVIER RAMOS JR
Drywall Nailing 6/6/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 6/6/2023 Approved JAVIER RAMOS JR
Insulation 6/6/2023 Approved JAVIER RAMOS JR
Service/Power Release 7/24/2023 Not Ready for Inspection WILLIAM WREN
Shower Pan 7/24/2023 Approved WILLIAM WREN
Drywall Nailing 10/10/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Final 10/10/2023 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 10/10/2023 Approved JAVIER RAMOS JR
Drywall Nailing 11/13/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/13/2023 Approved JAVIER RAMOS JR
Pre-Inspection 11/13/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/20/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/20/2023 Approved JAVIER RAMOS JR
Final 12/20/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/20/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 12/20/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/20/2023 Approved JAVIER RAMOS JR
Final 1/9/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 1/9/2024 Approved JAVIER RAMOS JR
Final 3/29/2024 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 3/29/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 3/29/2024 Approved JAVIER RAMOS JR
Service/Power Release 3/29/2024 Approved JAVIER RAMOS JR