10136 N GLORIA AVE 91343
Certificate Information: 10136 N GLORIA AVE 91343
- Application / Permit
- 22014-20000-03507
- Plan Check / Job No.
- B22VN10785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert existing 2-Car Garage, plus addition into ADU PER LAMC 12.22 A.33 (c)-(d) "The LID clearance has been deferred. Approval for LID requirements shall be obtained form LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 10/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2022 | RACHEL BEYENE |
| Corrections Issued | 7/25/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/19/2022 | ADAM HEGAZI |
| Plan Check Approved | 10/3/2022 | RAHEL BEYENE |
| Issued | 10/7/2022 | APPLICANT |
| CofO in Progress | 4/1/2024 | JAVIER RAMOS JR |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 8/24/2022 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 8/30/2022 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 9/22/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/17/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/9/2023 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 3/21/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 3/24/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| Special/Order Compliance | 4/19/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/1/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 5/1/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/1/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/1/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/3/2023 | Partial Approval | MICHEL ABAJAN |
| Insulation | 5/12/2023 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/18/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 5/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 6/6/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 6/6/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| Shower Pan | 7/24/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/10/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 10/10/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/13/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/13/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 11/13/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/20/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/20/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/20/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/20/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 12/20/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/20/2023 | Approved | JAVIER RAMOS JR |
| Final | 1/9/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/29/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 3/29/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/29/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/29/2024 | Approved | JAVIER RAMOS JR |