917 E 74TH ST 90001

Certificate Information: 917 E 74TH ST 90001

Application / Permit
22014-20000-03506
Plan Check / Job No.
B22VN10784
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Existing garage 200 sq.f. with new addition 296 Sq.f. to be convert in A.D.U. 496 Sq.t. total
Permit Issued
Issued on 4/1/2023
Issuing Office
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 JOE VO
Corrections Issued 7/23/2022 JOE VO
Plan Check Approved 2/23/2023 JOE VO
Issued 4/1/2023 APPLICANT
CofO in Progress 6/14/2024 MICHAEL LEWIS
CofO in Progress 6/14/2024 DAVID FEILER
CofO in Progress 6/24/2024 MICHAEL LEWIS
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/13/2023 ABEL CASILLAS
Roof/Waste drainage to street Cleared 1/13/2023 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 2/13/2023 ABEL CASILLAS
Sewer availability Cleared 2/13/2023 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 4/26/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 4/28/2023 Partial Approval MICHAEL LEWIS
Deputy Drilled-In Anchors 5/5/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/9/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 8/25/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 8/25/2023 Approved MICHAEL LEWIS
Sewer 8/25/2023 Approved MICHAEL LEWIS
Underground Mechanical 8/25/2023 Approved MICHAEL LEWIS
HVAC-Rough 9/5/2023 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 9/5/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/21/2023 Approved MICHAEL LEWIS
Insulation 12/29/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 12/29/2023 Approved MICHAEL LEWIS
Shower Pan 12/29/2023 Approved MICHAEL LEWIS
Drywall Nailing 2/7/2024 Approved MICHAEL LEWIS
Drywall Nailing 2/9/2024 Approved JOSE MACIAS
Service/Power Release 3/18/2024 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 5/24/2024 Approved CRAIG DAVIS
Final 5/24/2024 Corrections Issued CRAIG DAVIS
Green Building Final 5/24/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 5/24/2024 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Approved CRAIG DAVIS
Smoke Detectors 5/24/2024 Approved CRAIG DAVIS
Green Building Final 6/4/2024 Approved MICHAEL LEWIS
HVAC-Final 6/4/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 6/4/2024 Not Ready for Inspection MICHAEL LEWIS
Final 6/13/2024 Not Ready for Inspection MICHAEL LEWIS
Service/Power Release 6/13/2024 Approved MICHAEL LEWIS
Special/Order Compliance 6/14/2024 Corrections Issued MICHAEL LEWIS
Final 6/17/2024 Corrections Issued MICHAEL LEWIS
Final 6/21/2024 OK to Issue CofO MICHAEL LEWIS