9351-9353 N CRYSTAL VIEW DR 91042
Certificate Information: 9351-9353 N CRYSTAL VIEW DR 91042
- Application / Permit
- 22014-20000-03495
- Plan Check / Job No.
- B22VN10757
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRR. 30'-5" X 14'-5" (276 SF) TO AND CONVERT (E) 11'-10" X 22' (263 SF) ATTACHED 1-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT (539 SQ FT) PER LAMC 12.22 A.33(c) and (e). ENCLOSE 11'-1" X 2'-10" (31 SF) AND REMODEL (E) SFD TO CREATE NEW 1/2 BTHRM AND COAT CLOSET & EXPAND (E) BDRM. WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | SERGIO MUNIZ |
| Corrections Issued | 7/13/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| Applicant returned to address corrections | 12/12/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 12/15/2022 | MADISON ODELL |
| No Progress | 1/31/2023 | ANGELICA MARTINEZ |
| Plan Check Approved | 2/16/2023 | ALEC MOUSAKHANIAN |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 12/13/2023 | DAVID ANDERSON |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
| CofO Issued | 1/10/2024 | RUBEN SALAS |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 8/17/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/18/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 9/30/2022 | GILBERT URREA |
| Specific Plan | Cleared | 10/3/2022 | CECILIA CASTILLO |
| Low Impact Development | Cleared | 11/9/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | COLIN LOREDO |
| GPI Written Notices | Cleared | 12/12/2022 | SERGIO MUNIZ |
| Grading Pre-Inspection | Cleared | 12/12/2022 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 4/19/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/21/2023 | Approved | DAVID ANDERSON |
| Grounding or Bonding | 4/21/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 4/21/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/7/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 6/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 6/7/2023 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 6/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 6/13/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/21/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/21/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/21/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 6/21/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/21/2023 | Approved | DAVID ANDERSON |
| Insulation | 7/13/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/13/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/18/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 8/1/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/3/2023 | Approved | THOMAS FINNILA |
| Underground Mechanical | 8/9/2023 | Partial Approval | DAVID ANDERSON |
| Gas Test | 10/4/2023 | Approved | DAVID ANDERSON |
| Final | 10/16/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 10/16/2023 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/16/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 12/12/2023 | OK to Issue CofO | DAVID ANDERSON |