6639 1/2 N SATSUMA AVE 91606

Certificate Information: 6639 1/2 N SATSUMA AVE 91606

Application / Permit
22014-20000-03490
Plan Check / Job No.
B22VN10742
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1196SF 2 STORY ADU AND TRELLIS ADDITION TO (E) DET. GARAGE 74 SF ADDITION TO (E) GARAGE DETACHED ADU PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 MAHNAZ NOURHASHEMI
Corrections Issued 8/11/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 8/26/2022 KEN GILL
Building Plans Picked Up 9/27/2022 APPLICANT
Plan Check Approved 4/6/2023 SUNMIN LEE
Issued 4/6/2023 APPLICANT
CofO in Progress 5/8/2025 JOSE AVILA
Permit Finaled 6/3/2025 RUBEN SALAS
CofO Issued 6/3/2025 RUBEN SALAS
Permit Finaled 6/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/21/2022 CARLOS AGUILERA
Construction near power lines Cleared 3/8/2023 RIDWAN HARDY
Low Impact Development Cleared 3/10/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/13/2023 CARLOS AGUILERA
Sewer availability Cleared 3/13/2023 CARLOS AGUILERA
Permit Cleared 3/21/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2024 Approved JOHN HAYES
PLUMBING-Rough 9/9/2024 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 9/11/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/16/2024 Corrections Issued JOSE AVILA
Sewer 9/16/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/17/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 10/16/2024 Approved JOSE AVILA
ELECTRICAL-Rough 10/18/2024 Approved JOSE AVILA
PLUMBING-Rough 10/18/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 11/22/2024 Approved JOSE AVILA
Green Building Rough 11/22/2024 Approved JOSE AVILA
HVAC-Rough 11/22/2024 Approved JOSE AVILA
Deputy Wood Construction 11/25/2024 Conditional Approval JUAN VALENZUELA
Insulation 12/4/2024 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 12/4/2024 Approved MICHAEL CORTEZ
Shower Pan 12/4/2024 Approved MICHAEL CORTEZ
Drywall Nailing 12/12/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Final 4/30/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/30/2025 Approved JOSE AVILA
Gas Test 4/30/2025 Approved JOSE AVILA
HVAC-Final 4/30/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 4/30/2025 Corrections Issued JOSE AVILA
Smoke Detectors 4/30/2025 Approved JOSE AVILA
ELECTRICAL-Final 5/7/2025 Approved JOSE AVILA
Final 5/7/2025 OK to Issue CofO JOSE AVILA
Green Building Final 5/7/2025 Approved JOSE AVILA
HVAC-Final 5/7/2025 Approved JOSE AVILA
PLUMBING-Final 5/7/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 5/7/2025 Approved JOSE AVILA