5657 N MAMMOTH AVE 91401
Certificate Information: 5657 N MAMMOTH AVE 91401
- Application / Permit
- 22014-20000-03482
- Plan Check / Job No.
- B22VN10736
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/15/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/18/2022 | DANIEL YIP |
| Plan Check Approved | 12/1/2022 | DANIEL YIP |
| No Progress | 12/2/2022 | DANIEL YIP |
| Plan Check Approved | 12/2/2022 | DANIEL YIP |
| Issued | 12/2/2022 | APPLICANT |
| CofO in Progress | 2/23/2024 | RYAN SALAZAR |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/22/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 9/16/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 4/27/2023 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/24/2023 | Approved | RYAN SALAZAR |
| Sewer | 5/24/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/2/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 6/7/2023 | Approved | RYAN SALAZAR |
| Insulation | 6/14/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/22/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 6/22/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/22/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/26/2023 | Approved | RYAN SALAZAR |
| Gas Test | 8/21/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 8/31/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | RYAN SALAZAR |
| Final | 2/21/2024 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/21/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 2/21/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 2/21/2024 | Approved | RYAN SALAZAR |