1040 N DEXTER ST 90042

Certificate Information: 1040 N DEXTER ST 90042

Application / Permit
22014-20000-03467
Plan Check / Job No.
B22VN10705
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
8'-0 X 30" ADDITION AND INTERIOR REMODEL TO THE EXISTING SINGLE FAMILY DWELLING - ALL WORK ENGINEER
Permit Issued
Issued on 8/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/13/2022 SERGIO MUNIZ
Corrections Issued 7/14/2022 SERGIO MUNIZ
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 8/19/2022 DANIEL ABRAMYAN
Issued 8/23/2022 APPLICANT
CofO in Progress 12/30/2022 HAMIK HARTOUNIAN
CofO Issued 1/18/2023 DEROLD HAUFF
Permit Finaled 1/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/25/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 7/28/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/28/2022 JEANIE LAM
Sewer availability Cleared 8/23/2022 JEANIE LAM

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B 13412 BURBANK BLVD # 3      SHERMAN OAKS, CA 91401
Engineer Bareng,, Jenn Tamayo; Lic. No.: C79168 21301 ERWIN ST #427      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/22/2022 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/22/2022 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 11/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/30/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/30/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 11/30/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/9/2022 Approved KATHRYN BUTTERWORTH
Insulation 12/9/2022 Approved KATHRYN BUTTERWORTH
Final 12/29/2022 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/29/2022 Approved HAMIK HARTOUNIAN
Green Building Final 12/29/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 12/29/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 1/11/2023 Partial Approval HAMIK HARTOUNIAN