17615-17617 W BLYTHE ST 91325
Certificate Information: 17615-17617 W BLYTHE ST 91325
- Application / Permit
- 22014-20000-03423
- Plan Check / Job No.
- B22VN10566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ATTACHED GARAGE CONVERSION TO JADU 298 SQ FT, 66 SF ADDITION (N) LAUNDRY to SFD.
- Permit Issued
- Issued on 1/14/2023
- Issuing Office
- Current Status
- CofO Issued on 9/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2022 | MINA HABILI |
| Corrections Issued | 7/18/2022 | MINA HABILI |
| Applicant returned to address corrections | 7/28/2022 | MINA HABILI |
| Applicant returned to address corrections | 8/8/2022 | MINA HABILI |
| Plan Check Approved | 9/9/2022 | JOSEPH RAFOLS |
| Issued | 1/14/2023 | APPLICANT |
| CofO in Progress | 9/13/2023 | RAUL OLAGI |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
| CofO Issued | 9/27/2023 | RUBEN SALAS |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/25/2022 | CARLOS AGUILERA |
Contact Information
| Architect | , ; Lic. No.: C33595 | , |
| Contractor | D U A Build; Lic. No.: 967782-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/3/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 3/23/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 3/23/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/18/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 4/18/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 5/23/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 5/23/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/23/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/23/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | RAUL OLAGI |
| Final | 9/12/2023 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 9/12/2023 | Approved | RAUL OLAGI |