5847 N SHIRLEY AVE 91356
Certificate Information: 5847 N SHIRLEY AVE 91356
- Application / Permit
- 22014-20000-03399
- Plan Check / Job No.
- B22VN09545
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN (N) Pool and SPA
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | JAD BASMA |
| Corrections Issued | 7/10/2022 | JAD BASMA |
| Quality Review Completed | 7/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/16/2022 | JAD BASMA |
| Plan Check Approved | 1/4/2023 | JAD BASMA |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 11/26/2024 | JON MCHUGH |
| No Progress | 1/13/2025 | JON MCHUGH |
| CofO in Progress | 1/13/2025 | JON MCHUGH |
| CofO in Progress | 1/27/2025 | JON MCHUGH |
| CofO Issued | 3/3/2025 | JOHN JANSON |
| Permit Finaled | 3/3/2025 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Corrections Issued | JON MCHUGH |
| Rough-Electrical | 10/17/2023 | Not Ready for Inspection | JON MCHUGH |
| Rough-Plumbing | 10/17/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 10/19/2023 | Not Ready for Inspection | JON MCHUGH |
| Pre-Gunite | 10/19/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 10/26/2023 | Corrections Issued | JON MCHUGH |
| Pre-Gunite | 10/26/2023 | Conditional Approval | JON MCHUGH |
| Deck | 2/14/2024 | Corrections Issued | JON MCHUGH |
| Deck | 2/27/2024 | Corrections Issued | JON MCHUGH |
| Deck | 3/1/2024 | Approved | JON MCHUGH |
| Enclosure/Fence | 5/20/2024 | Corrections Issued | MORRIS JACKSON |
| Enclosure/Fence | 5/22/2024 | Corrections Issued | JON MCHUGH |
| Deck | 6/25/2024 | Approved | JON MCHUGH |
| Enclosure/Fence | 6/25/2024 | Approved | JON MCHUGH |
| Equipment Noise Level | 11/6/2024 | Approved | FELIPE PENICHE |
| Deputy Shotcrete | 11/12/2024 | Conditional Approval | JON MCHUGH |
| Final | 11/12/2024 | Corrections Issued | JON MCHUGH |
| Enclosure/Fence | 11/26/2024 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Approved | JON MCHUGH |
| Final | 11/26/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 11/26/2024 | Approved | JON MCHUGH |
| Green Building Rough | 11/26/2024 | Approved | JON MCHUGH |
| Pre-Gunite | 11/26/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | JON MCHUGH |
| Special/Order Compliance | 1/13/2025 | Corrections Issued | JON MCHUGH |
| Final | 1/27/2025 | OK to Issue CofO | JON MCHUGH |