6502 N ORION AVE 91406

Certificate Information: 6502 N ORION AVE 91406

Application / Permit
22014-20000-03389
Plan Check / Job No.
B22VN10521
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO GARAGE FOR NEW ADU. GARAGE TO REMAIN.
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
Issued on 1/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/9/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 JOE VO
Corrections Issued 7/15/2022 JOE VO
Applicant returned to address corrections 12/23/2022 SUNMIN LEE
Plan Check Approved 1/18/2023 JOE VO
Issued 1/23/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/14/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/15/2022 COLIN LOREDO
Sewer availability Cleared 9/15/2022 COLIN LOREDO
ZI Cleared 1/3/2023 JASON CHAN
Low Impact Development Cleared 1/4/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/5/2023 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/4/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 5/4/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 5/31/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved RYAN SALAZAR
PLUMBING-Rough 8/8/2023 Partial Approval RYAN SALAZAR
Sewer 8/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/29/2024 Partial Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 1/29/2024 Corrections Issued ROBERT GOLD
Rough-Elec/Plmb/HVAC 3/21/2024 Approved RYAN SALAZAR
Insulation 4/17/2024 Approved RYAN SALAZAR
Drywall Nailing 5/14/2024 Approved RYAN SALAZAR
Final 8/19/2025 No Access for Inspection JOSE AVILA
BUILDING-Rough-Frame 9/3/2025 Approved RYAN SALAZAR
Final 9/3/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 9/3/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 9/3/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 9/3/2025 Not Ready for Inspection RYAN SALAZAR
Final 10/16/2025 Partial Approval RYAN SALAZAR
Green Building Final 10/16/2025 Approved RYAN SALAZAR
Smoke Detectors 10/16/2025 Approved RYAN SALAZAR
Final 1/26/2026 Corrections Issued JAVIER RAMOS JR