6502 N ORION AVE 91406
Certificate Information: 6502 N ORION AVE 91406
- Application / Permit
- 22014-20000-03389
- Plan Check / Job No.
- B22VN10521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO GARAGE FOR NEW ADU. GARAGE TO REMAIN.
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- Issued on 1/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | JOE VO |
| Corrections Issued | 7/15/2022 | JOE VO |
| Applicant returned to address corrections | 12/23/2022 | SUNMIN LEE |
| Plan Check Approved | 1/18/2023 | JOE VO |
| Issued | 1/23/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/15/2022 | COLIN LOREDO |
| ZI | Cleared | 1/3/2023 | JASON CHAN |
| Low Impact Development | Cleared | 1/4/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/5/2023 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/4/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 5/4/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/31/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | RYAN SALAZAR |
| Sewer | 8/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/29/2024 | Partial Approval | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 1/29/2024 | Corrections Issued | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 3/21/2024 | Approved | RYAN SALAZAR |
| Insulation | 4/17/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/14/2024 | Approved | RYAN SALAZAR |
| Final | 8/19/2025 | No Access for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | RYAN SALAZAR |
| Final | 9/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 9/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 9/3/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 10/16/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 10/16/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 10/16/2025 | Approved | RYAN SALAZAR |
| Final | 1/26/2026 | Corrections Issued | JAVIER RAMOS JR |