7765-7767 S ISIS AVE 90045
Certificate Information: 7765-7767 S ISIS AVE 90045
- Application / Permit
- 22014-20000-03379
- Plan Check / Job No.
- B22VN10479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17' X 28'-2" ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | OMAR GARNICA |
| Corrections Issued | 7/13/2022 | OMAR GARNICA |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Plan Check Approved | 9/13/2022 | DANIEL SANJUAN |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 5/3/2024 | BOBBY KEY |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
| CofO Issued | 5/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 8/9/2022 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/11/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 8/15/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | CATHERINE ADROVER |
Contact Information
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 12/15/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 12/20/2022 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/3/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 6/30/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/22/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 12/22/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/22/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/3/2024 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 1/3/2024 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 1/3/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 1/11/2024 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 1/11/2024 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 1/11/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 1/11/2024 | Partial Approval | BOBBY KEY |
| Shower Pan | 1/11/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | BOBBY KEY |
| Green Building Rough | 1/25/2024 | Approved | BOBBY KEY |
| Insulation | 1/25/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | BOBBY KEY |
| Shower Pan | 1/25/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 2/8/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 4/8/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 4/8/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 4/8/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/12/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 4/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 4/26/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 4/26/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/3/2024 | Approved | BOBBY KEY |
| Final | 5/3/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 5/3/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/3/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 5/3/2024 | Approved | BOBBY KEY |