8645 N WAKEFIELD AVE 91402
Certificate Information: 8645 N WAKEFIELD AVE 91402
- Application / Permit
- 22014-20000-03369
- Plan Check / Job No.
- B22VN10458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 15'-7"X13' addition at rear of existing one story single family dewlling per WFPP
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2022 | AUNG SOE |
| Corrections Issued | 7/12/2022 | AUNG SOE |
| Applicant returned to address corrections | 8/3/2022 | AUNG SOE |
| Plan Check Approved | 8/9/2022 | AUNG SOE |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 8/5/2023 | GREGG CUMMINGS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 7/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/30/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 11/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/8/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/19/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/31/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 1/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/29/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/29/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 3/29/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/14/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/14/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/14/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 4/14/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 4/14/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/24/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/5/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/22/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/19/2023 | Corrections Issued | DAVID MATSON |
| Green Building Final | 7/19/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 7/19/2023 | Approved | DAVID MATSON |
| Final | 7/27/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/4/2023 | Approved | GREGG CUMMINGS |
| Final | 8/4/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/4/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/4/2023 | Approved | GREGG CUMMINGS |