8645 N WAKEFIELD AVE 91402

Certificate Information: 8645 N WAKEFIELD AVE 91402

Application / Permit
22014-20000-03369
Plan Check / Job No.
B22VN10458
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: 15'-7"X13' addition at rear of existing one story single family dewlling per WFPP
Permit Issued
Issued on 8/18/2022
Issuing Office
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/12/2022 AUNG SOE
Corrections Issued 7/12/2022 AUNG SOE
Applicant returned to address corrections 8/3/2022 AUNG SOE
Plan Check Approved 8/9/2022 AUNG SOE
Issued 8/18/2022 APPLICANT
CofO in Progress 8/5/2023 GREGG CUMMINGS
Permit Finaled 9/11/2023 RUBEN SALAS
CofO Issued 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/18/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 7/18/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/18/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 7/18/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 7/18/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 7/18/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/29/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 11/30/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 11/30/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/8/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 12/14/2022 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 1/19/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/31/2023 Corrections Issued GREGG CUMMINGS
Green Building Rough 1/31/2023 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/29/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/29/2023 Approved CHRISTOPHER DELLEFIELD
Wood Frame 3/29/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/14/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 4/14/2023 Approved GREGG CUMMINGS
Green Building Rough 4/14/2023 Approved GREGG CUMMINGS
HVAC-Rough 4/14/2023 Approved GREGG CUMMINGS
Shower Pan 4/14/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/24/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/24/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 5/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/1/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 5/5/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/22/2023 Approved CHRISTOPHER DELLEFIELD
Final 7/19/2023 Corrections Issued DAVID MATSON
Green Building Final 7/19/2023 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved DAVID MATSON
Smoke Detectors 7/19/2023 Approved DAVID MATSON
Final 7/27/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Final 8/4/2023 Approved GREGG CUMMINGS
Final 8/4/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 8/4/2023 Approved GREGG CUMMINGS
PLUMBING-Final 8/4/2023 Approved GREGG CUMMINGS