1827 W 41ST ST 90062

Certificate Information: 1827 W 41ST ST 90062

Application / Permit
22014-20000-03363
Plan Check / Job No.
B22VN10439
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 2/4/2025
Issuing Office
Metro
Current Status
Issued on 2/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/13/2022 HAYATO TSUCHIYA
Corrections Issued 8/13/2022 HAYATO TSUCHIYA
Building Plans Picked Up 8/25/2022 APPLICANT
Applicant returned to address corrections 8/22/2023 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/2/2024 NEHEMIAS RAMOS
Plan Check Approved 2/6/2024 JOSEPH RAFOLS
Issued 2/4/2025 APPLICANT

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 10/2/2023 RAFAEL FONTES
Historic monument Cleared 10/2/2023 RAFAEL FONTES
Construction near power lines Cleared 12/22/2023 WALTER RAMIREZ
Address approval Cleared 1/18/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 1/18/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 1/18/2024 JILVER MAZARIEGOS
Sewer availability Cleared 1/18/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/20/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 2/26/2025 Partial Approval SABAS ALONSO
Underground Mechanical 2/26/2025 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 4/18/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 4/18/2025 Corrections Issued SABAS ALONSO
Pre-Inspection 4/30/2025 Approved ANTHONY RAMOS
ELECTRICAL-Rough 5/13/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 5/13/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/27/2025 Approved SABAS ALONSO
Green Building Rough 6/27/2025 Approved SABAS ALONSO
HVAC-Rough 6/27/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 6/27/2025 Approved SABAS ALONSO
Insulation 12/11/2025 Approved ANTHONY RAMOS
Drywall Nailing 12/22/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 1/13/2026 Approved SABAS ALONSO