7645 N AMESTOY AVE 91406
Certificate Information: 7645 N AMESTOY AVE 91406
- Application / Permit
- 22014-20000-03360
- Plan Check / Job No.
- B22VN10418
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 16' X 10' ADDITION TO (E) SFD TO RELOCATE KITCHEN , ENCLOSE 5' X 4' PORTION OF PORCH TO CONVERT TO HABITABLE SPACE AS PART OF THE ENTRY, INTERIOR REMODEL TO (E) SFD TO REMODEL LAUNDRY , CONVERT KITCHEN TO DINING ROOM , REMODEL LIVING ROOM , BATHROOM , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | RARES BODEA |
| Corrections Issued | 7/25/2022 | RARES BODEA |
| Quality Review Completed | 7/27/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/29/2022 | APPLICANT |
| Plan Check Approved | 9/22/2022 | RARES BODEA |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | RAUL OLAGI |
| CofO in Progress | 3/6/2024 | JUAN VALENZUELA |
| No Progress | 3/6/2024 | JUAN VALENZUELA |
| Permit Finaled | 5/14/2024 | RUBEN SALAS |
| CofO Issued | 5/14/2024 | RUBEN SALAS |
| Permit Finaled | 5/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/25/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 8/29/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | COLIN LOREDO |
Contact Information
| Contractor | Quality Tech Construction Inc; Lic. No.: 1026398-B | 967 ROYAL AVENUE SIMI VALLEY, CA 93065 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/14/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/9/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/9/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/9/2023 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 2/10/2023 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 3/1/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 3/8/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 3/8/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 3/8/2023 | Approved | RAUL OLAGI |
| Insulation | 3/8/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/8/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/31/2023 | Approved | RAUL OLAGI |
| Shower Pan | 3/31/2023 | Approved | RAUL OLAGI |
| Grounding or Bonding | 4/21/2023 | Not Ready for Inspection | RAUL OLAGI |
| Final | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/25/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| Final | 2/15/2024 | OK to Issue CofO | RAUL OLAGI |
| Smoke Detectors | 2/15/2024 | Approved | RAUL OLAGI |