18779 W PASADERO DR 91356
Certificate Information: 18779 W PASADERO DR 91356
- Application / Permit
- 22014-20000-03358
- Plan Check / Job No.
- B22VN10416
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION TO (E) SFD, INT./EXT. REMODEL AND ENTIRELY NEW ROOF FRAMING
- Permit Issued
- Issued on 1/29/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | CARLOS MONTES |
| Corrections Issued | 8/8/2022 | CARLOS MONTES |
| Quality Review Completed | 8/11/2022 | KEN GILL |
| Applicant returned to address corrections | 7/26/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 8/31/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 9/14/2023 | CARLOS MONTES |
| Plan Check Approved | 11/29/2023 | CARLOS MONTES |
| Issued | 1/29/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | JOHN KIDWELL |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
| CofO Issued | 4/18/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/29/2022 | RYAN KIM |
| BHO/Hillside ordinance | Cleared | 12/29/2022 | RYAN KIM |
| BHO/Hillside ordinance | Cleared | 12/29/2022 | RYAN KIM |
| BHO/Hillside ordinance | Cleared | 12/29/2022 | RYAN KIM |
| BHO/Hillside ordinance | Cleared | 12/29/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | RYAN KIM |
| Grading Pre-Inspection | Cleared | 2/2/2023 | CARLOS MONTES |
| GPI Written Notices | Cleared | 2/16/2023 | CARLOS MONTES |
| Hydrant and Access approval | Cleared | 3/8/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 5/23/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/12/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/4/2024 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/21/2024 | Corrections Issued | JOHN KIDWELL |
| Underground Mechanical | 6/21/2024 | Partial Approval | JOHN KIDWELL |
| Insulation | 6/28/2024 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/4/2024 | Partial Inspection | JOHN KIDWELL |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 9/4/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 9/9/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/8/2024 | Approved | JOHN COLEMAN |
| HVAC-Rough | 11/8/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 11/8/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/5/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/5/2024 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/5/2024 | Approved | JOHN KIDWELL |
| Insulation | 12/13/2024 | Approved | SEAN WIRCH |
| Drywall Nailing | 12/19/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/4/2025 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 2/4/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 2/7/2025 | Approved | SCOTT SOBEL |
| Final | 8/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/1/2025 | Approved | JOHN KIDWELL |
| Green Building Final | 8/1/2025 | Conditional Approval | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 8/1/2025 | Approved | JOHN KIDWELL |
| Final | 8/14/2025 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 8/14/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | JOHN KIDWELL |
| Final | 8/22/2025 | Conditional Approval | JOHN KIDWELL |
| Green Building Final | 8/22/2025 | Approved | JOHN KIDWELL |
| Final | 9/8/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Special/Order Compliance | 9/15/2025 | Corrections Issued | JOHN KIDWELL |
| Final | 9/25/2025 | OK to Issue CofO | JOHN KIDWELL |