4376 N IRVINE AVE 91604

Certificate Information: 4376 N IRVINE AVE 91604

Application / Permit
22014-20000-03352
Plan Check / Job No.
B22VN10398
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADD 1ST AND 2ND STORY ADDITIONS TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 SELLA BENYAMIN
Corrections Issued 8/8/2022 SELLA BENYAMIN
Quality Review Completed 8/10/2022 STEVEN KIM
Building Plans Picked Up 8/12/2022 APPLICANT
Plan Check Approved 9/8/2022 SELLA BENYAMIN
Issued 9/15/2022 APPLICANT
CofO in Progress 11/8/2024 CHRISTOPHER ROJAS
CofO in Progress 11/8/2024 CHRISTOPHER ROJAS
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/10/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/10/2022 JOSE DUARTE-DIAZ
ZI Cleared 8/19/2022 MIGUEL GAMBOA
Low Impact Development Cleared 8/23/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/24/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/29/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/12/2024 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 4/9/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 4/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/16/2024 Not Ready for Inspection KEVIN BERBERYAN
Pre-Inspection 6/7/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/24/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Gas Test 6/24/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 6/24/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 6/28/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 7/3/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/3/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/8/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 7/8/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/17/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 7/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/17/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/24/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 7/24/2024 Approved CHRISTOPHER ROJAS
Insulation 7/31/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 8/2/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/5/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 8/12/2024 Not Ready for Inspection MICHAEL CORTEZ
Drywall Nailing 8/15/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/22/2024 Approved CHRISTOPHER ROJAS
Shower Pan 8/22/2024 Approved CHRISTOPHER ROJAS
Pre-Inspection 9/25/2024 Approved CHRISTOPHER ROJAS
Final 10/7/2024 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 10/15/2024 Partial Inspection CHRISTOPHER ROJAS
Final 10/15/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/15/2024 Partial Inspection CHRISTOPHER ROJAS
Final 10/18/2024 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/18/2024 Approved CHRISTOPHER ROJAS
Final 11/8/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 11/8/2024 Approved CHRISTOPHER ROJAS