11925 S LINDBLADE DR 90230
Certificate Information: 11925 S LINDBLADE DR 90230
- Application / Permit
- 22014-20000-03351
- Plan Check / Job No.
- B22VN10397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. 2-CAR GARAGE TO ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33 (c)-(d)) WITH NEW 2ND FLOOR 14'-11" x 31'-11" ADDITION AND 5'-5" x 14'-4" ADDITION TO 1ST FLOOR AND NEW PATIO COVER
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- Issued on 12/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/5/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/24/2022 | APPLICANT |
| Applicant returned to address corrections | 12/6/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 12/19/2022 | SEAN SHAHMIRI |
| Issued | 12/19/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/6/2022 | JENSON LEE |
| Address approval | Cleared | 9/14/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | JENSON LEE |
| Specific Plan | Cleared | 9/19/2022 | ROBERT SANCHEZ |
| Construction near power lines | Cleared | 11/21/2022 | NADER ISKANDER |
Contact Information
| Contractor | Double 88 Construction Inc; Lic. No.: 1052973-B | 1925 CENTURY PARK EAST STE 1700 LOS ANGELES, CA 90067 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/28/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/28/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/28/2023 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 2/28/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/10/2023 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 4/12/2023 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 4/13/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 4/13/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/21/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/21/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/28/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 5/5/2023 | Approved | HERBERT GIRON |
| Insulation | 5/5/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Pre-Inspection | 8/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 9/19/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 9/19/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 9/19/2023 | Approved | HERBERT GIRON |
| Final | 3/13/2026 | Corrections Issued | DAVID FEILER |