924 S NORTON AVE 90019
Certificate Information: 924 S NORTON AVE 90019
- Application / Permit
- 22014-20000-03308
- Plan Check / Job No.
- B22VN10287
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 33' 5" X 28' 9" TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 7/5/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/11/2022 | APPLICANT |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 5/8/2023 | JEFFREY MEAD |
| CofO in Progress | 5/16/2023 | SCOTT FINNILA |
| CofO in Progress | 5/17/2023 | SCOTT FINNILA |
| CofO in Progress | 5/17/2023 | SCOTT FINNILA |
| Permit Finaled | 5/18/2023 | DEROLD HAUFF |
| CofO Issued | 5/18/2023 | DEROLD HAUFF |
| Permit Finaled | 5/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 7/19/2022 | AMANDA KAINER |
| Low Impact Development | Cleared | 7/27/2022 | AMMAR ELTAWIL |
| Address approval | Cleared | 7/30/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/30/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/30/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 9/19/2022 | PATRICK MAGALLANES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/20/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/28/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 10/28/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/1/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 12/1/2022 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/1/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 12/8/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 12/8/2022 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 12/8/2022 | Approved | JEFFREY MEAD |
| Insulation | 12/13/2022 | Corrections Issued | JEFFREY MEAD |
| Insulation | 12/16/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/27/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 12/27/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/6/2023 | Approved | JEFFREY MEAD |
| Final | 3/16/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/16/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 3/16/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/8/2023 | Approved | JEFFREY MEAD |
| Final | 5/8/2023 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 5/8/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/8/2023 | Approved | JEFFREY MEAD |