4345 N ELMER AVE 91602
Certificate Information: 4345 N ELMER AVE 91602
- Application / Permit
- 22014-20000-03303
- Plan Check / Job No.
- B22VN10270
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 3'-6" X 16'-10" ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNITT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- CofO Issued on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/6/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Applicant returned to address corrections | 1/11/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 1/30/2024 | JESSE ARELLANO |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 11/6/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 11/8/2024 | RAUL OLAGI |
| Permit Finaled | 11/14/2024 | DANIEL ORRANTE |
| CofO Issued | 11/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/7/2022 | MEGAN GODINEZ |
| ZI | Cleared | 2/2/2023 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 1/29/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 3/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Drilled-In Anchors | 3/7/2024 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 3/7/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 3/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 5/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/13/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/5/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/5/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/5/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Wood Frame | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/14/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/17/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/8/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Shower Pan | 7/8/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/11/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 7/18/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 11/6/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/6/2024 | Approved | CHRISTOPHER ROJAS |