4345 N ELMER AVE 91602

Certificate Information: 4345 N ELMER AVE 91602

Application / Permit
22014-20000-03303
Plan Check / Job No.
B22VN10270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
3'-6" X 16'-10" ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNITT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/9/2024
Issuing Office
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 ARTIN ZARUKIAN
Corrections Issued 7/6/2022 ARTIN ZARUKIAN
Building Plans Picked Up 7/6/2022 APPLICANT
Applicant returned to address corrections 1/11/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 1/30/2024 JESSE ARELLANO
Issued 2/9/2024 APPLICANT
CofO in Progress 11/6/2024 CHRISTOPHER ROJAS
CofO in Progress 11/8/2024 RAUL OLAGI
Permit Finaled 11/14/2024 DANIEL ORRANTE
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/6/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/6/2022 MEGAN GODINEZ
Sewer availability Cleared 7/7/2022 MEGAN GODINEZ
ZI Cleared 2/2/2023 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/6/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 2/6/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 2/6/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 2/6/2023 MEGAN GODINEZ
Construction near power lines Cleared 1/29/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 3/6/2024 Not Ready for Inspection KIRK SANDERS
Deputy Drilled-In Anchors 3/7/2024 Conditional Approval JUAN VALENZUELA
Underground Mechanical 3/7/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 3/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/12/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/13/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/13/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 5/13/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/13/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 5/13/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/13/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 5/14/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/5/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/11/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 6/11/2024 Approved CHRISTOPHER ROJAS
Insulation 6/11/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/11/2024 Partial Approval CHRISTOPHER ROJAS
Wood Frame 6/11/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/14/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 6/17/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/8/2024 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 7/8/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/11/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 7/18/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/1/2024 Approved CHRISTOPHER ROJAS
Final 10/1/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 10/1/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 10/1/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 10/1/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 10/1/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/1/2024 Approved CHRISTOPHER ROJAS
Final 11/6/2024 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/6/2024 Approved CHRISTOPHER ROJAS