9014 N GAYNOR AVE 91343
Certificate Information: 9014 N GAYNOR AVE 91343
- Application / Permit
- 22014-20000-03291
- Plan Check / Job No.
- B22VN10231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RECREATION ROOM INTO A A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 10/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/9/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Plan Check Approved | 10/21/2022 | LAWRENCE QUIRANTE |
| Issued | 10/21/2022 | APPLICANT |
| CofO in Progress | 10/10/2023 | RAUL OLAGI |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
| CofO Issued | 10/23/2023 | RUBEN SALAS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/12/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 9/26/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/7/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/7/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 8/7/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 8/7/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/7/2023 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 8/7/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/9/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 8/9/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/9/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 8/9/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/9/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 8/9/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | RAUL OLAGI |
| Insulation | 8/18/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/25/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 9/29/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/29/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 9/29/2023 | Approved | RAUL OLAGI |
| Final | 10/10/2023 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | RAUL OLAGI |