18551 W VICTORY BLVD 91335
Certificate Information: 18551 W VICTORY BLVD 91335
- Application / Permit
- 22014-20000-03283
- Plan Check / Job No.
- B22VN10213
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE WITH 1ST AND 2ND FLOOR ADDITION TO NEW ACCESSORY DWELLING UNIT ( 23'-0"X32'-0" )PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/17/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Plan Check Approved | 11/7/2022 | MOHAMMAD ESMAILI |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 4/3/2023 | JON MCHUGH |
| CofO in Progress | 4/3/2023 | JON MCHUGH |
| Permit Finaled | 4/12/2023 | JOHN JANSON |
| CofO Issued | 4/12/2023 | JOHN JANSON |
| Permit Finaled | 4/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/21/2022 | CARLOS AGUILERA |
| ZI | Cleared | 10/5/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 10/27/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | CARLOS AGUILERA |
Contact Information
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/16/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 11/17/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Corrections Issued | SEAN HAUPT |
| Wood Frame | 12/1/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 12/27/2022 | Approved | JON MCHUGH |
| PLUMBING-Rough | 12/27/2022 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 1/3/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/3/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 1/4/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 1/4/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 1/5/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/9/2023 | Approved | VINCENT HANLEY |
| Insulation | 1/9/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 1/9/2023 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 1/9/2023 | Partial Inspection | JESUS PINEDA |
| Underground Mechanical | 1/9/2023 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 1/17/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/17/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 2/6/2023 | Approved | JON MCHUGH |
| Final | 2/17/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 2/17/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 2/17/2023 | Approved | JON MCHUGH |
| Final | 2/24/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Approved | JON MCHUGH |
| Final | 3/2/2023 | Partial Approval | JON MCHUGH |
| Service/Power Release | 3/2/2023 | Approved | JON MCHUGH |
| Final | 4/3/2023 | OK to Issue CofO | JON MCHUGH |