18551 W VICTORY BLVD 91335

Certificate Information: 18551 W VICTORY BLVD 91335

Application / Permit
22014-20000-03283
Plan Check / Job No.
B22VN10213
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE WITH 1ST AND 2ND FLOOR ADDITION TO NEW ACCESSORY DWELLING UNIT ( 23'-0"X32'-0" )PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 MOHAMMAD ESMAILI
Corrections Issued 7/17/2022 MOHAMMAD ESMAILI
Quality Review Completed 7/18/2022 OMID HEDAYAT
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 11/7/2022 MOHAMMAD ESMAILI
Issued 11/10/2022 APPLICANT
CofO in Progress 4/3/2023 JON MCHUGH
CofO in Progress 4/3/2023 JON MCHUGH
Permit Finaled 4/12/2023 JOHN JANSON
CofO Issued 4/12/2023 JOHN JANSON
Permit Finaled 4/12/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/20/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/21/2022 CARLOS AGUILERA
Sewer availability Cleared 7/21/2022 CARLOS AGUILERA
ZI Cleared 10/5/2022 DANG NGUYEN
Low Impact Development Cleared 10/27/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/27/2022 CARLOS AGUILERA

Contact Information

Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/16/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/17/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 11/17/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Corrections Issued SEAN HAUPT
Wood Frame 12/1/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Corrections Issued JON MCHUGH
HVAC-Rough 12/27/2022 Approved JON MCHUGH
PLUMBING-Rough 12/27/2022 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 1/3/2023 Approved JON MCHUGH
PLUMBING-Rough 1/3/2023 Approved JON MCHUGH
ELECTRICAL-Rough 1/4/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 1/4/2023 Approved JON MCHUGH
ELECTRICAL-Rough 1/5/2023 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 1/9/2023 Approved VINCENT HANLEY
Green Building Rough 1/9/2023 Approved VINCENT HANLEY
Insulation 1/9/2023 Approved VINCENT HANLEY
Shower Pan 1/9/2023 Approved VINCENT HANLEY
Special/Order Compliance 1/9/2023 Partial Inspection JESUS PINEDA
Underground Mechanical 1/9/2023 Partial Approval VINCENT HANLEY
Drywall Nailing 1/17/2023 Approved JON MCHUGH
Interior/Exterior Lathing 1/17/2023 Approved JON MCHUGH
Underground Mechanical 2/6/2023 Approved JON MCHUGH
Final 2/17/2023 Corrections Issued JON MCHUGH
Green Building Final 2/17/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 2/17/2023 Approved JON MCHUGH
Final 2/24/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Approved JON MCHUGH
Final 3/2/2023 Partial Approval JON MCHUGH
Service/Power Release 3/2/2023 Approved JON MCHUGH
Final 4/3/2023 OK to Issue CofO JON MCHUGH