14151 W RAVEN ST 91342

Certificate Information: 14151 W RAVEN ST 91342

Application / Permit
22014-20000-03264
Plan Check / Job No.
B22VN10171
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: addtion at rear of existing one story single family dewlling with attached garage. remodel and new deck. per engineer design
Permit Issued
Issued on 8/7/2022
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/12/2022 AUNG SOE
Corrections Issued 7/12/2022 AUNG SOE
Plan Check Approved 8/3/2022 JOSEPH RAFOLS
Issued 8/7/2022 APPLICANT
CofO in Progress 3/20/2023 ARAM AVEDISIAN
Permit Finaled 4/11/2023 MICHAEL SMITH
CofO Issued 4/11/2023 MICHAEL SMITH
Permit Finaled 4/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 8/2/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Ursu,, Dragos Marian; Lic. No.: C79963 343 S MADISON AVE APT 19      PASADENA, CA 91101
Engineer Ursu,, Dragos Marian; Lic. No.: NA79963       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 11/10/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/22/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 11/22/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Corrections Issued ARAM AVEDISIAN
Green Building Rough 12/14/2022 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/21/2022 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 12/29/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/29/2022 Corrections Issued ARAM AVEDISIAN
Green Building Rough 12/29/2022 Approved ARAM AVEDISIAN
HVAC-Rough 12/29/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 12/29/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 12/29/2022 OK to Expire Permit ARAM AVEDISIAN
ELECTRICAL-Rough 1/3/2023 Approved ARAM AVEDISIAN
Insulation 1/3/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/3/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 1/3/2023 Approved ARAM AVEDISIAN
Drywall Nailing 1/6/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/6/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 2/28/2023 Approved MICHEL ABAJAN
Final 2/28/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 2/28/2023 Approved MICHEL ABAJAN
HVAC-Final 2/28/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/28/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/28/2023 Approved MICHEL ABAJAN
Final 3/20/2023 OK to Issue CofO ARAM AVEDISIAN