17321 W VICTORY BLVD 91406
Certificate Information: 17321 W VICTORY BLVD 91406
- Application / Permit
- 22014-20000-03263
- Plan Check / Job No.
- B22VN10168
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 39'-2" x 39'-1" IRREGULAR SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO A (N) IRREGULAR SHAPED DETACHED 39'-2"x 41'-7" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/2/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Plan Check Approved | 10/3/2022 | ALFRED RAMIREZ |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 1/23/2024 | JON MCHUGH |
| Permit Finaled | 3/22/2024 | JOHN JANSON |
| CofO Issued | 3/22/2024 | JOHN JANSON |
| Permit Finaled | 3/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| ZI | Cleared | 7/18/2022 | NATHAN ROMINE |
| Construction near power lines | Cleared | 8/4/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/20/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | D H Property Maintenance Inc; Lic. No.: 985811-B | 11312 COVELLO STREET SUN VALLEY, CA 91352 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 12/7/2022 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 12/13/2022 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | JON MCHUGH |
| Special/Order Compliance | 12/28/2022 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 2/9/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 3/7/2023 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 3/7/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 4/11/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 4/11/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 4/11/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/18/2023 | Approved | JON MCHUGH |
| Insulation | 4/18/2023 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 4/18/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 4/28/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/28/2023 | Partial Approval | JOHN KIDWELL |
| Final | 12/13/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 12/13/2023 | Approved | JON MCHUGH |
| Green Building Final | 12/13/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 12/13/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/23/2024 | Approved | JON MCHUGH |
| Final | 1/23/2024 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 1/23/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/23/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | JON MCHUGH |